Construction Rate Analysis Calculator
Choose an item of work, enter local material rates and wages, wastage, sundries and overhead to build the unit rate per cubic metre or 10 square metres and the cost of your quantity.
Runs in your browser. Your files never leave your device. See how to check
…
How to do it
- 1Choose the item
RCC, PCC, brick.
- 2Enter quantity
In the item unit.
- 3Enter material rates
Local prices.
- 4Enter wages
Mason and helper.
- 5Set additions
Wastage, overhead.
- 6Download CSV
Rate sheet.
About this tool
Rate analysis is how engineers and contractors work out what one unit of construction work costs, such as one cubic metre of reinforced concrete or ten square metres of plaster. It is the method behind the schedules of rates published by the Central Public Works Department and state PWDs, and behind every serious estimate. The rate is built up from the quantities of each material needed per unit of work, plus an allowance for wastage, the labour needed in mason-days and helper-days, a small allowance for water, tools and sundries, and finally the contractor's overhead and profit, usually 10% to 15%. For concrete, the nominal mix ratio decides the materials: M20 at 1:1.5:3 needs about eight bags of cement, 0.42 cubic metres of sand and 0.84 cubic metres of aggregate per cubic metre of finished concrete, after allowing for the dry volume. Brickwork in 1:6 mortar needs about 500 bricks per cubic metre and the cement and sand for the mortar. Plaster depends on thickness and mix. Labour productivity varies with site and skill, which is why local rates matter. Because material prices and wages change often, a schedule of rates can be out of date, and householders building a house need to check whether a contractor's rate is fair. This calculator lets you choose common items, enter local rates for cement, sand, aggregate, steel, bricks and tiles and daily wages for masons and helpers, set wastage, sundries and overhead, and see the material and labour breakdown, the unit rate and the cost for your quantity. Download the analysis as a CSV to compare with quotes or include in an estimate.
Who this is for
Civil engineers and students, contractors pricing tenders, house owners checking quotes, and site supervisors planning material orders.
Typical material coefficients
| Item | Cement | Sand | Aggregate / bricks | |---|---|---|---| | RCC M20 (1:1.5:3), per m³ | 8.06 bags | 0.42 m³ | 0.84 m³ | | PCC 1:4:8, per m³ | 3.4 bags | 0.47 m³ | 0.94 m³ | | Brickwork 1:6, per m³ | 1.57 bags | 0.33 m³ | 500 bricks | | Plaster 12 mm 1:4, per 10 m² | 0.88 bag | 0.13 m³ | – |
Steel in RCC
Steel varies by member: slabs about 60 to 90 kg per m³, beams 110 to 150 kg and columns 150 kg or more. Use the bar bending schedule for an exact figure.
Overhead and profit
CPWD analyses usually add 15% for contractor's profit and overheads. Small works may use 10%.
Shuttering
Formwork is often analysed as a separate item per square metre of contact area.
Using the results
Multiply each unit rate by the measured quantity from drawings to build an estimate. Compare with local schedules of rates and contractor quotes.
Limits
Coefficients are typical for nominal mixes; design mixes and local practice differ. This is an estimating aid, not a structural design or tender estimate.
Worked example
M20 RCC with cement at ₹390 a bag, sand ₹2,200 and aggregate ₹1,900 per m³, steel 90 kg at ₹68, mason ₹950 and helper ₹650 a day, 3% wastage, 1.5% sundries and 15% overhead: about ₹16,412 per m³, or about ₹1.97 lakh for 12 m³.
Quick facts
- Category: Money & Tax
- Works in your browser, no sign-up, no upload.
- Your input stays on your device.
- Available in English.
- Content last reviewed:
- Official source: CPWD
Frequently asked questions
What is rate analysis?
Working out the cost of one unit of work from materials, labour, sundries and overhead.
How many cement bags are in 1 m³ of M20?
About 8 bags for a nominal 1:1.5:3 mix.
How many bricks are in 1 m³ of brickwork?
About 500 standard bricks.
What overhead is usual?
About 15% in CPWD analyses.
Does it include steel?
For RCC, yes, at the kg per m³ you enter.
Is my data stored?
Only in your browser.