Construction Rate Analysis Calculator: RCC, Brick, Plaster

Build unit rates for RCC, PCC, brickwork, plaster and tiling from local material prices, wages, wastage, sundries and overhead, then cost your quantity.

Saizul Amin
Saizul Amin5 Nov 2026 · 4 min read
Construction Rate Analysis Calculator: RCC, Brick, Plaster

Rate analysis is how engineers and contractors work out the cost of one unit of construction work, such as a cubic metre of concrete or ten square metres of plaster. It is the method behind CPWD and state PWD schedules of rates, and behind any serious estimate. The free Construction Rate Analysis Calculator builds that rate from your own local prices and wages.

Your figures stay in your browser.

What rate analysis is

A unit rate is built up in layers:

  1. Materials per unit of work, from standard coefficients, plus a wastage allowance.
  2. Labour in mason-days and helper-days, priced at local daily wages.
  3. Sundries for water, tools and small items, as a percentage.
  4. Overhead and profit for the contractor, usually 10% to 15%.

Because material prices and wages change often, a published schedule can be out of date for your site. Building the rate yourself shows what a fair price looks like today.

Why it matters

House owners use rate analysis to check whether a contractor's quote is reasonable. Contractors use it to price tenders. Site supervisors use the material quantities to plan orders. Students use it to learn how estimates are made.

How to use the calculator

  1. Choose the item: RCC M20 (per m3), PCC 1:4:8 (per m3), brickwork in 1:6 mortar (per m3), 12 mm plaster in 1:4 (per 10 m2) or vitrified tile flooring (per 10 m2).
  2. Enter the quantity in the item's unit.
  3. For RCC, enter the steel in kg per m3.
  4. Enter local rates for the cement bag, sand, aggregate, steel, bricks, tiles and adhesive, as needed for the item.
  5. Enter the mason and helper daily wages.
  6. Set wastage %, sundries % and overhead and profit %.
  7. Read the rate per unit, the cost for your quantity, and the materials and labour totals.
  8. Review the material, labour and build-up tables, and download the CSV if you need it.

You can also save different price sets as Compare presets, for example two suppliers' cement and steel rates.

A worked example

RCC M20 with these local prices:

InputValue
CementRs 390 a bag
SandRs 2,200 per m3
AggregateRs 1,900 per m3
Steel90 kg per m3 at Rs 68 a kg
MasonRs 950 a day
HelperRs 650 a day
Wastage3%
Sundries1.5%
Overhead and profit15%

The calculator gives about Rs 16,412 per m3. For 12 m3 of concrete the cost comes to about Rs 1.97 lakh. If a contractor quotes far above that for the same specification, you have a basis to ask why.

Material coefficients

ItemCementSandAggregate / bricks
RCC M20 (1:1.5:3), per m38.06 bags0.42 m30.84 m3
PCC 1:4:8, per m33.4 bags0.47 m30.94 m3
Brickwork 1:6, per m31.57 bags0.33 m3500 bricks
Plaster 12 mm 1:4, per 10 m20.88 bag0.13 m3-

These are typical figures for nominal mixes. For M20, about eight bags of cement go into one cubic metre of finished concrete after allowing for the dry volume of the mix.

Steel in RCC

Steel varies a lot by member. Slabs often need about 60 to 90 kg per m3, beams 110 to 150 kg, and columns 150 kg or more. The bar bending schedule from your structural drawings gives the exact figure, so use it in place of a typical value when you have one.

Overhead and profit

CPWD analyses usually add 15% for the contractor's profit and overheads. Small works may use 10%. If you are hiring labour directly and buying materials yourself, you can lower or remove this figure to see your own cost.

Using the results

Multiply each unit rate by the measured quantity from your drawings to build an estimate. Formwork (shuttering) is usually analysed as a separate item per square metre of contact area, so add it separately for RCC work. Compare your totals with the local schedule of rates and with contractor quotes.

Tips

  • Use prices from your nearest suppliers, including delivery to site.
  • Check wages with local masons; productivity varies by site and skill.
  • Keep wastage realistic. Tiles and bricks often break more than you expect on small jobs.
  • Save the CSV with each estimate so you can update it when prices change.

Limits

Coefficients are typical for nominal mixes; design mixes and local practice differ. This is an estimating aid, not a structural design or a tender estimate.

Frequently asked questions

What is rate analysis?

Working out the cost of one unit of work from materials, labour, sundries and overhead.

How many cement bags are in 1 m3 of M20 concrete?

About 8 bags for a nominal 1:1.5:3 mix.

How many bricks are in 1 m3 of brickwork?

About 500 standard bricks.

What overhead is usual?

About 15% in CPWD analyses, sometimes 10% for small works.

Does the RCC rate include steel?

Yes, at the kg per m3 you enter.

Final thoughts

The Construction Rate Analysis Calculator turns local prices into a clear unit rate you can defend. Compare it with the schedules published by CPWD (cpwd.gov.in) or your state PWD. This guide is general information, not professional engineering advice.