Sprint Burndown Chart Maker

Type committed story points and, day by day, the points completed and any scope added or removed to get a burndown chart, velocity, the pace needed to finish, an on-track check and SVG and CSV downloads.

ทำงานในเบราว์เซอร์ของคุณ ไฟล์ไม่ออกจากอุปกรณ์ ดูวิธีตรวจสอบ

…

วิธีทำ

  1. 1
    Sprint

    Name it and enter committed points.

  2. 2
    Days

    Add a row per working day.

  3. 3
    Log

    Enter points done each day.

  4. 4
    Scope

    Record added or removed work.

  5. 5
    Share

    Download the SVG chart.

เกี่ยวกับเครื่องมือนี้

The Sprint Burndown Chart Maker turns a short daily log into the chart most scrum teams look at during stand-up and again at the retrospective. You give the sprint a name, enter the story points the team committed to at planning, and fill in one row per working day. Each row has a day label, the points completed that day and a scope change column where added work is a positive number and removed work is negative. From that log the tool draws three lines. The ideal line falls in a straight line from the committed total on the first day to zero on the last. The actual line shows the points still remaining after each day. The scope line shows the total size of the sprint, so you can see at a glance whether a flat stretch was caused by slow progress or by new work being pulled in. Days after the last one with any activity are treated as not yet happened, so the chart is useful in the middle of a sprint, not only at the end. Alongside the chart the results show points remaining, points completed so far, average velocity per day, the points per day needed to finish on time, the net scope change and a plain verdict: on track at the current pace, behind, finished or not finished. Two downloads make the chart easy to share. Chart as SVG gives a crisp vector image titled with the sprint name, with the three lines and a legend, which opens in any browser and drops straight into slides. Data CSV gives the day, completed points, scope change, remaining and ideal values for a spreadsheet. The tool works with story points, hours or task counts, as long as you use one unit for the whole sprint.

Who this is for

Scrum masters and team leads who do not want to fight a project tool for one chart, small teams tracking work on a whiteboard, students learning agile, and anyone who needs a clean burndown image for a sprint review.

How to use it

1. Name the sprint and enter the committed points. The default is Sprint 24 with 42 points. 2. Add one row per working day. The default is a two-week sprint of ten days, Mon 1 to Fri 10. 3. Each day, type the points finished. Count a story only when it meets your definition of done. 4. When work is added or removed, enter it in the scope column on the day it happened. 5. Read the verdict, then download the SVG for slides or the CSV for your records.

What the default sprint shows

Eight days have activity. The team finished 33 points and, after 3 points were added on day 3 and 2 removed on day 7, the sprint grew by a net 1 point to 43. Ten points remain. The average so far is about 4.1 points a day, but finishing in the last two days needs 5 a day, so the verdict reads Behind: re-plan or cut scope. On the chart the actual line sits at 10 on day 8 while the ideal line is at about 9.3, and the orange scope line shows the bump on Wednesday. Remaining work went 42, 37, 37, 31, 29, 21, 15, 10; the flat step on day 3 is the added scope cancelling that day's progress.

Reading the shape

A line that tracks the ideal is the rare good case. A line that stays flat for days and then drops sharply usually means stories are too large to finish in a day or two, so splitting them makes the chart more honest. A line that rises means scope grew faster than the team delivered. If the actual line ends above zero often, the team is over-committing at planning; use the velocity figure from past sprints to set the next commitment.

Comparing sprints

Press + Sprint to add a tab for the next sprint and fill it in as you go. Compare all shows each sprint's remaining points, velocity, needed pace and scope change side by side, and stars the lowest remaining and lowest needed pace. Export comparison CSV saves that view, and Print / PDF report prints every sprint with its chart and figures. The project is saved automatically on your device; use Export JSON to back it up.

Limits

A burndown shows the quantity of work left, not its value or quality, and story points are team estimates rather than measurements. The ideal line assumes even progress across every listed day, so leave out weekends and holidays. Treat the verdict as a prompt for conversation, not a performance score or management advice about individuals.

ตัวอย่างพร้อมวิธีทำ

A 42-point sprint with 33 points done after eight of ten days and a net 1 point of added scope has 10 points left and needs 5 a day to finish.

สรุปสั้น ๆ

คำถามที่พบบ่อย

What is the ideal line?

A straight line from the committed points on the first day to zero on the last listed day. It assumes the same amount of work is finished every day.

How do I record scope changes?

Enter added points as a positive number and removed points as a negative number in the scope column on the day it happened.

Can I use it mid-sprint?

Yes. Days after the last row with activity are treated as not yet happened, so velocity and the needed pace use only the days so far.

How do I get the chart into slides?

Press Chart as SVG. The file opens in any browser and can be inserted into most slide tools as an image.

Can I track hours instead of story points?

Yes. Use any single unit for the whole sprint, such as hours or tasks; the maths is the same.

Why does the verdict say behind?

The points per day needed to finish are higher than the average the team has managed so far.