Project Planner With Gantt Timeline, Dependencies and Critical Path

Add tasks with owners, durations and dependencies; the planner schedules them on working days, finds the critical path and overloads, and exports CSV or an .ics calendar.

Runs in your browser. Your files never leave your device. See how to check

…

How to do it

  1. 1
    Set up the project

    Enter the name, start date and holidays.

  2. 2
    Add tasks

    Give each task an owner, duration and dependencies.

  3. 3
    Check the schedule

    Read start, finish, slack and the critical path.

  4. 4
    Use the views

    Board for status, timeline for dates, workload for people.

  5. 5
    Export

    Download CSV, the calendar file or the SVG timeline.

About this tool

A to-do list tells you what needs doing; a project plan tells you when it can be done, what depends on what, and which tasks decide the finish date. Project management software does this well but is expensive, and free tiers often hide the timeline and workload views. This planner shows the same tasks four ways. In the list you enter each task's name, owner, duration in working days and the tasks it depends on, and update status and percent complete. The planner then schedules every task using the critical path method developed by Kelley and Walker in 1959: a forward pass gives each task its earliest start and finish after its predecessors, and a backward pass gives the latest dates that would not delay the project. The difference is slack. Tasks with no slack form the critical path, highlighted in red: delay any of them and the whole project slips. Milestones with zero duration mark key dates. Weekends and the holidays you list are skipped. The board view moves tasks between To do, Doing and Done. The timeline draws a Gantt chart with dependency arrows, progress bars, milestones and weekends shaded, which you can zoom and export as SVG. The workload view counts working days per person per week and flags weeks where someone is booked for more days than exist, caused by overlapping tasks.

Who it is for

Small business owners, freelancers juggling client projects, team leads, students planning theses and event organisers.

Key terms

| Term | Meaning | |---|---| | Duration | Working days of effort for the task | | Dependency | Task B starts after task A finishes (finish-to-start) | | Critical path | The chain of tasks with zero slack that sets the finish date | | Slack (float) | Days a task can slip without delaying the project | | Milestone | A zero-duration checkpoint, such as Launch |

Using the critical path

Speeding up a task that has slack does not bring the finish date forward. To finish earlier, shorten critical tasks, add people to them, or run them in parallel by changing dependencies.

Workload

Two tasks for the same person in the same week can add up to more than five working days. The workload view shows these overloads so you can reassign or reorder.

Exports

CSV opens in any spreadsheet. The .ics file adds every task and milestone as an all-day event to Google Calendar, Outlook or Apple Calendar.

Limits

Only finish-to-start dependencies are supported, all tasks use the same calendar, and resources are not levelled automatically. For large programmes with cost tracking, use dedicated project software.

Worked example

A website relaunch: requirements 3 days, design 5, build 10, help pages 4 and testing 5, with launch as a milestone. Requirements, design, build and testing form the critical path of 23 working days; the help pages have 11 days of slack.

Privacy

Plans stay in your browser; export the project file to back up or share.

Worked example

Relaunch: critical path 23 working days; help pages have 11 days of slack.

Quick facts

Frequently asked questions

How do I find the critical path?

Enter tasks with durations and dependencies; tasks in red have zero slack and form the critical path.

Can I make a Gantt chart for free?

Yes, the timeline view draws one and exports SVG.

Does it skip weekends and holidays?

Yes, unless you choose to work on weekends.

What is slack?

How many days a task can be delayed without delaying the project.

Can I export to my calendar?

Yes, as an .ics file.

Where is my plan stored?

In your browser; export it to back it up.

Guides for this tool

Completely freeNo cost, no sign-up
Files stay privateEverything runs in your browser
Easy in your languageAvailable in many languages