Excavation Grid Calculator

Enter the site size, unit size and datum coordinates to get unit labels and corner coordinates, diagonals for squaring, and the excavated and spoil volumes.

Runs in your browser. Your files never leave your device. See how to check

…

How to do it

  1. 1
    Enter the site size

    East-west and north-south.

  2. 2
    Enter the unit size

    Square units.

  3. 3
    Enter the datum

    Origin easting and northing.

  4. 4
    Choose labels

    Letter-number or coordinates.

  5. 5
    Enter depth and bulking

    For spoil volume.

About this tool

Archaeological excavations are controlled with a grid of square units tied to a fixed datum, so every find and feature can be recorded in three dimensions. This calculator plans such a grid: it counts the units, labels them either as letter-number squares (A1, B1...) or by their south-west corner coordinates (N500E1000), lists the corner coordinates, gives the unit and site diagonals and a 3-4-5 triangle for squaring corners, and estimates the excavated and spoil volumes for a chosen depth.

Who this is for

Archaeology students, field directors, community excavation groups, surveyors and teachers planning a training dig.

The site grid

A grid is laid out from a datum point with known coordinates, often a survey nail or peg tied to the national grid. Units are typically 1 × 1 m, 2 × 2 m or 5 × 5 m. Every unit is named, and finds are recorded by unit, layer (context) and position.

Labelling systems

- **Letter-number**: columns A, B, C... from west to east and rows 1, 2, 3... from south to north. Easy to read on site. - **Coordinate**: each unit takes the coordinates of its south-west corner, for example N500E1000. Unambiguous when the grid is extended in any direction, and favoured in North American practice.

Choose one system at the start and keep it for the whole project.

Setting out right angles

Use the 3-4-5 triangle: from a corner, measure 3 units along one line and 4 along the other; the diagonal between these points is exactly 5 when the angle is 90°. The calculator scales the triangle to your unit size. Check finished units by measuring both diagonals: in a square they are equal to the side × √2 (2.828 m for a 2 m unit).

Baulks

Many excavations leave baulks, strips of unexcavated soil (often 0.5–1 m) between units, to keep sections visible. Plan the grid lines on the baulk centres or on unit edges consistently.

Spoil

Excavated soil expands as it loosens. A bulking factor of about 20–30 % is typical for loose soil, more for clay and rubble. Spoil heaps should be placed away from the trench edge, outside the area of future work, and sorted if needed for sieving or backfilling.

Recording

- Total station or GNSS for accurate coordinates. - Levels relative to the site datum for heights. - Plans and sections at 1:20 or 1:10 within each unit.

Good practice

Mark the site datum permanently and record it in the archive. Re-check the grid every day, since pegs move.

Health and safety

Trenches deeper than about 1.2 m need shoring or stepping back, and spoil must be kept back from edges. Follow your country's rules and the excavation director's risk assessment.

Worked example

A 10 × 8 m area with 2 m units from a datum at E1000, N500 gives 5 × 4 = 20 units (A1–E4), covering 80 m². Each unit's diagonal is 2.83 m; a 1.2-1.6-2.0 m triangle sets the corner. Excavating 0.5 m deep removes 40 m³ of soil, producing about 50 m³ of spoil at 25 % bulking.

Limits

Planning arithmetic only; follow the official standards of your excavation authority.

Worked example

10 × 8 m in 2 m units = 20 units, 40 m³ excavated at 0.5 m, 50 m³ of spoil.

Quick facts

Frequently asked questions

What size should excavation units be?

Commonly 1 × 1 m or 2 × 2 m for detailed work, 5 × 5 m for open areas.

How do I set a right angle?

Use a 3-4-5 triangle and check both unit diagonals.

What is the SW-corner naming system?

Each unit is named by the coordinates of its south-west corner.

What is a bulking factor?

The increase in volume when soil is dug, typically 20–30 %.

What is a baulk?

An unexcavated strip left between units to show the section.

Is my data stored?

No. Everything is calculated in your browser.

Guides for this tool

Completely freeNo cost, no sign-up
Files stay privateEverything runs in your browser
Easy in your languageAvailable in many languages