Change Order Log
Record every change to the contract, track approvals, see the running contract value and added days, and print change orders to sign.
Runs in your browser. Your files never leave your device. See how to check
…
How to do it
- 1Enter the contract
Set original value and duration in Settings.
- 2Raise changes
Add description, cost and time impact.
- 3Submit
Print the change order for signature.
- 4Approve
Record the approval date and approver.
- 5Watch the totals
See the running contract value.
- 6Report
Print the log for the final account.
About this tool
Changes are normal on building projects, but unrecorded or unapproved changes are a major cause of disputes and unpaid work. This log keeps every change order, also called a variation, in one place for contractors, builders and clients. Enter the original contract value and duration in Settings. Then add each change order with the date, number, project, description and who requested it: the client, the designer, the contractor, an unexpected site condition or a regulation. Enter the cost impact, positive for extra work or negative for omissions, and the time impact in days, write the scope and pricing details, and track the status from Draft and Submitted to Approved, Rejected or Void with the approval date and approver. Only approved changes update the running contract value, which appears against every row so you can see how the contract sum has grown. Stats show the original contract, approved changes, current contract value, pending changes, the change as a percentage of the original and the days added. Insights remind you not to start unapproved work and list changes waiting more than two weeks. The board shows changes by status, the summary groups them by who requested them, and each change order prints with signature lines for both parties.
Who this is for
General contractors, builders, renovation companies, subcontractors, project managers and clients who want a clear record of contract changes.
Change order basics
| Field | Purpose | |---|---| | Description and details | Exactly what changes in the scope | | Cost impact | Price of extra work or credit for omitted work | | Time impact | Days added to or removed from the programme | | Requested by | Who caused the change, which affects who pays | | Approval | Written agreement before work starts |
Get approval first
Starting extra work on a verbal instruction is risky: the client may later dispute the price or deny asking for it. Price the change, get it signed, then do the work. For urgent changes, at least confirm the instruction in writing the same day.
Who pays?
Client requests and design changes are usually paid by the client. Unforeseen site conditions, such as rock in the footings, depend on the contract terms. Contractor errors are normally the contractor's cost. Recording who requested each change helps at the final account.
Worked example
A $250,000 contract has three approved changes: triple glazing (+$3,200, 3 days), extra excavation for rock (+$5,400, 4 days) and omitting a garden wall (−$2,100, −2 days). The current contract value is $256,500, a 2.6% increase, with 5 days added. A skylight worth $1,850 is still awaiting approval.
Limits
This log is a record and document template, not legal advice. Follow the change procedure in your contract. Data stays in your browser.
Worked example
$250,000 contract + $6,500 approved changes = $256,500 (2.6%), 5 days added; $1,850 pending.
Quick facts
- Category: Business & Work
- Works in your browser, no sign-up, no upload.
- Your input stays on your device.
- Available in English.
- Content last reviewed:
- Official source: AIA G701 change order practice; construction contract variations
Frequently asked questions
Which changes affect the contract value?
Only approved change orders; pending ones are shown separately.
Can I record credits for omitted work?
Yes, enter a negative cost and negative days.
Can I print a change order to sign?
Yes, the printer button prints it with contractor and client signature lines.
Can I track several projects?
Enter the project on each change; use one log per project for separate contract values.
What is the change percentage?
Approved changes as a percentage of the original contract value.
Is this legal advice?
No, follow your contract's change procedure.
