Construction Change Orders: Getting Paid for Extra Work Without Disputes

What a change order is, why written approval comes first, pricing cost and time impacts, who pays for what and keeping a running contract value.

Saizul Amin
Saizul Amin2 Nov 2026 · 3 min read
Construction Change Orders: Getting Paid for Extra Work Without Disputes

Almost no building project ends exactly as it was drawn. Clients change their minds, designers revise details and the ground hides surprises. Each change alters the price and often the time needed. Recording changes properly is the difference between being paid for extra work and arguing about it at the end of the job.

What a change order is

A change order, called a variation in many countries, is a written agreement to change the scope of a construction contract. It describes the change, states the effect on price and time, and is signed by both parties. Changes can add work, such as an extra skylight, or remove it, such as omitting a garden wall, which gives the client a credit.

Approval before work

The golden rule is to get written approval before doing extra work. Verbal instructions on site are easy to give and easy to forget or dispute. Price the change, write it up and get it signed. If something truly urgent must be done immediately, at least confirm the instruction in writing the same day, by email or message, and follow with a formal change order.

Price both cost and time

Every change has a cost impact and a time impact. Extra work needs materials, labour and supervision, and it may push back other activities. A credit for omitted work should reflect the true saving. Include the effect on the completion date, because time disputes can be as costly as money disputes, especially where delay damages apply.

Who pays?

Changes requested by the client or the designer are normally paid by the client. Unexpected site conditions, such as rock, contamination or hidden services, depend on the contract: some put the risk on the contractor, others on the client. Changes required by a building inspector may be a design issue or a workmanship issue. Recording who requested each change helps settle these questions quickly.

Keep a running contract value

Keep a log of every change with its status: draft, submitted, approved, rejected or void. Only approved changes alter the contract sum. A running total shows the current contract value after each approved change, and a separate total shows pending changes still awaiting a decision. Both parties then know where the budget stands.

A worked example

A $250,000 home extension has three approved changes. The client asks for triple-glazed kitchen windows, adding $3,200 and three days. Rock found in the footings needs extra excavation, adding $5,400 and four days. The client then omits a garden wall, a credit of $2,100 and two days. The current contract value is $256,500, a 2.6% increase on the original, with five days added. A skylight priced at $1,850 has been submitted but not yet approved, so it is not included until the client signs.

Watch the cumulative effect

Individually small changes add up. Reviewing the log monthly with the client avoids a shock at the final account and gives a chance to decide whether further changes are affordable.

What a good change order contains

A clear change order includes a unique number, the date, the project, a precise description of what is added or removed, any drawings or specifications it refers to, a pricing breakdown of labour, materials, plant and margin, the effect on the completion date and signature lines for both parties. Numbering changes in sequence makes it easy to refer to them in meetings and invoices. Attach supporting quotes from subcontractors where relevant. When a change is rejected or withdrawn, mark it void rather than deleting it, so the history remains complete and nobody wonders later what happened to a missing number. At the end of the job, the change log forms the backbone of the final account.

Limits

This guide is general information. Contracts set out their own change procedures, notice periods and valuation rules, so follow your contract and take advice on disputed or large changes.