How to Plan a Project with a Gantt Chart and the Critical Path
Learn to break a project into tasks, link dependencies, find the critical path and slack, and share a clear Gantt chart as an image or spreadsheet.

How to Plan a Project with a Gantt Chart and the Critical Path
Every project, from a website launch to an office move, raises the same questions: what needs to happen, in what order, and when will it be finished? A Gantt chart answers them visually, and the critical path method tells you which tasks you must watch most closely. This guide explains both ideas in plain terms and shows how to apply them with the free Gantt Chart Maker.
Step one: list the work
Write down every piece of work that produces something: requirements, designs, content, build, testing, training. Keep tasks between a day and two weeks long. Shorter tasks clutter the chart, while longer ones hide problems until it is too late. Add milestones for moments that matter, such as sign-off or go-live; they have no duration and appear as diamonds.
Step two: estimate durations
Estimate each task in working days, ideally with the person who will do it. Turn on Skip weekends so that a five-day task means five working days. If a task crosses a public holiday, add a day, because only weekends are skipped automatically.
Step three: link the dependencies
Most tasks cannot start until another one finishes. Testing waits for the build, the build waits for the design. In the table, type the row numbers of the tasks a task waits for in the After column. With auto-schedule on, the tool starts each task as soon as everything before it is finished, unless you set a later start date yourself. Change one estimate and every following task moves, which is exactly what happens in real projects.
Step four: find the critical path
Once tasks are linked, some chains of work are longer than others. The longest chain from start to finish decides the end date; that is the critical path. The tool calculates it with a forward pass, which finds the earliest start of every task, and a backward pass from the finish, which finds the latest each task could start without delaying the end. The difference is slack, also called float. Tasks with zero slack are critical and turn red.
This is the most useful insight a plan gives you. If a task with eight days of slack runs three days late, nothing changes. If a critical task slips by a day, the launch slips by a day. Put your best people, your attention and any extra budget on the red bars.
Step five: adjust and track
Drag a bar to move a task, or drag its right end to change its length; the table updates and the critical path is recalculated. As work progresses, enter the percentage done for each task. The summary shows a weighted completion figure in which long tasks count more than short ones, and a dashed line marks today, so you can see at a glance whether the work is ahead of or behind the plan.
Sharing the plan
Export a PNG or PDF for status reports and emails. The XLSX export contains one row per task with real date cells, durations, dependencies, progress, slack and a critical flag, ready for filtering or further analysis in Excel or Google Sheets. Save the project file to continue later; the plan is also stored in your browser.
Know the method's limits
This tool models finish-to-start links only, without lags or resource levelling, which is enough for most small and medium projects. A plan is a forecast, not a promise: review it weekly, update estimates honestly and re-check the critical path whenever something changes.