How to Make an Electrical Load Schedule for a House or Shop
List circuits, size breakers and cables, check voltage drop and balance phases, then print a clean load schedule for your electrician or the utility.

Before a flat is wired, a shop is fitted out or a house gets a new connection, someone has to decide how many circuits the distribution board needs, what breaker protects each one, what cable it uses and how big the main switch should be. That decision is written down in a load schedule. Utilities ask for one when you apply for a connection or extra load, and owners who have one can compare contractors' quotes on equal terms.
What goes into a load schedule
A load schedule is a table with one row per circuit. Each row records what the circuit feeds, how many points it has, the wattage of each point, the total connected load, the demand expected at one time, the design current, the breaker rating, the cable size, the length of the run and the phase it is on. At the bottom are the panel totals: connected load, maximum demand, current per phase, main breaker and incoming cable.
Planning the circuits
Group the loads sensibly. Lighting is usually split into two or three circuits so a single fault does not black out the whole home. Ordinary sockets go on their own circuits by area, and heavy appliances such as air conditioners, geysers, cookers and pumps each get a dedicated circuit. Kitchens often have a power circuit for the fridge, oven and blender.
Using the maker
Open the Electrical Load Schedule Maker and enter the project name, address, board name and supply, single-phase or three-phase. Then add the circuits. For each one choose the type, enter the number of points and watts per point, a demand percentage, the phase and the cable length from the board to the far end.
Demand percentage reflects real use. Lights and air conditioners may run at full load together, so 100% is normal. Sockets are rarely all used at once, so 50% to 60% is common.
How sizes are chosen
For each circuit the tool divides the load by the voltage and a typical power factor for that kind of circuit to get the design current. It multiplies by a size factor, 1.25 by default, and picks the next standard miniature circuit breaker, never below a sensible minimum for the circuit type. It then picks the smallest copper cable whose current rating covers the breaker, using a table based on IEC 60364-5-52 for cable in conduit in an insulated wall.
Long runs lose voltage. The tool works out the voltage drop for the run, and if it exceeds the limit you set, 4% by default, it moves up a cable size until the drop is acceptable or flags the circuit if no listed size will do.
Phases and the main switch
On a three-phase board, assign circuits to R, Y and B. The summary shows the current on each phase and warns if they differ by more than 20%, with a hint about which phase to move a circuit from and to. A well-balanced board keeps the neutral current low and lets you use a smaller main switch.
The highest phase current, times the size factor, gives the suggested main breaker, and the cable table gives a suggested incoming cable.
Printing and sharing
The schedule prints as two A4 pages: the circuit table with totals, then the panel summary, phase table, warnings, your notes and signature lines for the preparer, checker and approver. You can also download it as a Word file to add a logo or edit the notes.
Checking a contractor's quote
When two electricians quote for the same job, ask each for a load schedule and compare them with yours. Large differences in breaker or cable sizes, or in the number of circuits, deserve a question. A quote that uses 1.5 mm² cable on a 20 A circuit, or puts every socket in the house on one breaker, is a warning sign.
Know the limits
The maker gives a first estimate based on the tables you load. It does not derate cables for grouping or high temperatures, check fault levels or breaker curves, or design earthing. A licensed electrician must confirm the design against your national code, whether that is the Bangladesh National Building Code, IS 732 or BS 7671, before any work starts.