Building Progress Payments: Deposit and Stage Limits by State

How deposits and progress payments work for home building contracts in NSW, Victoria and Queensland, including legal limits and when to pay.

Saizul Amin
Saizul Amin29 Oct 2026 · 3 min read
Building Progress Payments: Deposit and Stage Limits by State

Building Progress Payments: Deposit and Stage Limits by State

Building a new home or a major renovation is usually paid in instalments rather than one lump sum. The schedule of those instalments matters: pay too much too early and you carry the risk if the builder stops work or becomes insolvent. State laws set limits to protect owners. This guide explains them and shows how to plan your schedule with the progress payment schedule tool.

How progress payments work

The contract sets a deposit, payable on signing, and a list of stages. When the builder reaches a stage, they send a progress claim. The owner checks the work and pays. Common stages are base (slab or footings), frame, lock-up (roof, external walls, windows and doors), fixing (internal linings, cabinets and fittings) and practical completion.

Deposit limits

In NSW the deposit for residential building work cannot be more than 10% of the contract price. In Victoria and Queensland the deposit is capped at 10% for contracts under A$20,000 and 5% for contracts of A$20,000 or more. Queensland allows a higher deposit in some cases where most of the work is done off site, such as a kit or modular home.

Victorian stage limits

Victoria goes further for new homes built through all stages. The Domestic Building Contracts Act limits the share of the contract price payable at each stage: base 20%, frame 25%, lock-up 20% and fixing 20%, with the balance on completion. A builder who asks for more at an earlier stage is in breach. Contracts for only some stages, such as a lock-up only contract, use different percentages that must still reflect the work done.

Using the tool

Choose your state and enter the contract price and deposit percentage. Then list each stage with its percentage, one per line. The tool shows the dollar amount at each stage, the deposit limit for your state and contract price, and the total of all payments. It warns you if the deposit is above the legal cap, if the stages do not add up to 100%, or if a Victorian stage percentage is above the statutory maximum.

A worked example

A family in Ballarat signs a A$480,000 contract for a new home. The deposit is 5%, A$24,000, within Victoria's limit for contracts of A$20,000 or more. The stages are base 20% (A$96,000), frame 25% (A$120,000), lock-up 20% (A$96,000), fixing 20% (A$96,000) and completion 10% (A$48,000). The total is 100% and every stage is within the limit, so the tool shows no warnings.

Before you pay a claim

Inspect the work before paying each stage. Many owners hire an independent building inspector for frame and pre-handover inspections. Check that the stage described in the contract has actually been reached; a frame stage, for example, often requires the frame to be inspected and approved by the building surveyor. If the work is not finished, you do not have to pay yet. Put any concerns in writing.

Lenders and drawdowns

If you have a construction loan, the bank releases money as each stage is completed, usually after its own valuer inspects. Make sure the contract stages match the lender's drawdown schedule, or you may have to fund a gap from savings.

Variations

Changes to the work, such as upgraded tiles or an extra window, should be agreed in writing with a price before the work is done. Variations are usually paid with the next progress claim, so add them to your plan.

Common mistakes

Signing a contract with a deposit above the limit, paying for materials in advance, and paying a stage before it is reached are the most common problems. Each one increases your risk if the builder fails.

Limits

Contracts can set their own stages within the law. This is general information, not legal advice; ask a building lawyer or your state regulator about your contract.