AIA G702 and G703 Style Pay Application Builder

Enter the project, contract sum, change orders and a schedule of values with previous, current and stored amounts; the tool prints a continuation sheet and a nine-line application summary.

Runs in your browser. Your files never leave your device. See how to check

…

How to do it

  1. 1
    Project

    Enter the parties and number.

  2. 2
    Terms

    Set retainage and prior certificates.

  3. 3
    Contract

    Add the sum and change orders.

  4. 4
    Lines

    Fill the schedule of values.

  5. 5
    Print

    Check the summary and sign.

About this tool

The G702 and G703 Style Pay Application Builder lays out a contractor's monthly request for payment in the arrangement most owners, architects and lenders already know: a summary page in the manner of the AIA G702 and a continuation sheet in the manner of the G703. It does not reproduce the AIA forms; it prints the same figures in its own layout. The first section holds the project name, the owner, the contractor, the architect, the application number, the period-to date, the retainage percentage and the total of previous certificates for payment. The second holds the original contract sum, the net change by change orders and the schedule of values, an editable table where each line has a description of work, its scheduled value, the amount completed in previous applications, the amount completed this period and the value of materials stored on site. From those rows the continuation sheet works out, for each line, the total completed and stored to date, the percent complete, the balance to finish and the retainage held, and it adds a totals row. The application summary then follows the familiar nine lines: the original contract sum, the change orders, the contract sum to date, the total completed and stored to date, the retainage, the total earned less retainage, the previous certificates, the current payment due and the balance to finish including retainage. Retainage is taken at one rate on both completed work and stored materials. If the schedule of values does not add up to the contract sum to date, an italic note under the summary shows both figures. The page ends with the contractor's certification that the work follows the contract documents and that earlier payments have been passed on to subcontractors and suppliers, with signature lines for the contractor and for the architect's certificate. Two checks flag any line billed above its scheduled value and a schedule of values that does not match the contract sum plus change orders.

Who this is for

General contractors and subcontractors who bill monthly against a schedule of values, project managers on jobs that do not require the official AIA documents, and owners checking a pay request before they approve it.

How to use it

1. Enter the project, owner, contractor, architect and application number. 2. Set the period-to date, the retainage rate and the previous certificates. 3. Type the original contract sum and the net change orders. 4. Fill in each schedule of values line with previous, current and stored amounts. 5. Read the checks and the summary, then print for signature.

What the example shows

Application 6 for the Riverside Library Renovation runs to October 31, 2026, with Northline Construction Co. billing the City of Riverside Public Works. The original contract sum is $980,000.00 and change orders add $36,500.00, so the contract sum to date is $1,016,500.00, matching the seven schedule of values lines. Demolition and structural steel are 100% complete, roofing is 87.5% with $6,000.00 of stored materials, electrical is 67.6% and interior finishes are 7.5%. Work completed and stored to date totals $599,000.00, made up of $424,000.00 from earlier periods, $157,000.00 this period and $18,000.00 stored.

How the payment due is reached

Retainage at 10% on $599,000.00 is $59,900.00, leaving $539,100.00 earned less retainage. Subtracting previous certificates of $381,600.00 gives a current payment due of $157,500.00. The balance to finish including retainage is $477,400.00, the contract sum to date less the amount earned. The previous certificates figure is typed in rather than worked out; in this sample it is the $424,000.00 of earlier work less 10% retainage, so make sure yours matches what was actually certified.

When the checks fire

A single line with a $100 scheduled value and $110 billed to date triggers the over-billing warning, and because that line no longer matches the contract sum the second warning appears as well. Both checks are reminders and do not block printing.

Drafts and versions

Keep each month's application as a saved version, duplicate it to start the next one and update the previous and current columns. Print it to PDF for the architect, or save a Word or HTML copy.

Limits

The tool uses one retainage rate for completed work and stored materials, and it does not reduce retainage at 50% completion or handle separate rates by line. It does not track change orders line by line or produce lien waivers. It is a billing aid and not legal or accounting advice; follow your contract's payment terms and any required official forms.

Worked example

Application 6: $599,000.00 completed and stored, $59,900.00 retainage at 10%, $127,100.00 current payment due.

Quick facts

Frequently asked questions

What are the G702 and G703?

They are AIA documents for a contractor's payment application: G702 is the summary and certificate, and G703 is the continuation sheet with the schedule of values.

Can I use this instead of the official AIA forms?

Only if your contract does not require them. The tool prints the same figures in its own layout and is not an AIA document.

How is retainage worked out?

The retainage percentage is applied to the total completed and stored to date, line by line and in total.

What does current payment due mean?

It is the total earned less retainage, minus the previous certificates for payment. It is the amount requested on this application.

Can I bill for stored materials?

Yes, if the contract allows it. Enter their value in the stored column; they count toward the total to date and carry retainage.

What if my schedule of values does not match the contract sum?

A check warns you and a note under the summary shows both totals. Fix the lines or the change orders before you submit.