Job Safety Analysis (JSA and JHA) Builder

List the steps of a job, the hazards in each one and the controls you will use, class each control by the hierarchy of controls, score likelihood and severity before and after, and print the colour-coded JSA with a worker sign-off sheet.

Runs in your browser. Your files never leave your device. See how to check

…

How to do it

  1. 1
    Job

    Enter the task, site, permits and PPE.

  2. 2
    Steps

    List the job steps in order.

  3. 3
    Hazards

    Add hazards and score the risk before controls.

  4. 4
    Controls

    Choose controls by type and score again.

  5. 5
    Sign-off

    Review warnings and print the worker sheet.

About this tool

The Job Safety Analysis (JSA and JHA) Builder writes the step-by-step hazard analysis that supervisors complete before a non-routine or higher-risk task, known as a JSA, a JHA or a task risk assessment depending on the company. The first section records the job or task, the site or location, who prepared it, the date, any permits needed and the required PPE, one item per line; the PPE list is printed as a single comma-separated line under the heading. The main section is a table of job steps. Every row has the step, its hazards, a likelihood and a severity score before controls, the controls, a control type and a second pair of scores after controls. Scores run from 1 to 5, and the printed JSA multiplies them to give a risk number from 1 to 25 in a coloured cell: 1 to 3 is low and green, 4 to 7 is medium and yellow, 8 to 14 is high and amber, and 15 to 25 is very high and red with white text. The control type is chosen from the hierarchy of controls: Eliminate, Substitute, Engineering control, Administrative control and PPE. A note under the table states the scoring rule and the order of the hierarchy so that a reader of the printout knows how the numbers were reached. The last section holds the emergency arrangements and the name or role of the approver. Three warnings run against every row: a step whose risk after controls is still 15 or more, a step whose risk after controls is higher than before, and a step with a very high starting risk that relies on PPE as its control type. A Print worker sign-off sheet button prints a separate page with a declaration and 14 blank rows for name, company, signature and date.

Who this is for

Maintenance and production supervisors planning a task, site safety officers and H&S coordinators who review task risk assessments, contractors asked for a JSA before starting work on a client site, and trainers teaching hazard identification.

How to use it

1. Describe the job, the location, the permits and the PPE. 2. Break the job into steps in the order they are done. 3. For each step write the hazards and score likelihood and severity. 4. Add the controls, choose the control type and score the risk again. 5. Read the warnings, have the JSA reviewed and print the sign-off sheet.

What the sample shows

The sample JSA covers changing a conveyor drive belt on conveyor line 2 in warehouse B, prepared by R. Das on November 9, 2026, with lockout tagout and a step platform as permits and four PPE items. It has five steps. Isolating and locking out the conveyor starts at likelihood 4 and severity 5, a red 20, and falls to a yellow 5 after locking at the main isolator, trying the start button and hanging a tag. Releasing belt tension starts at 12 and drops to 4 once the tensioner is backed off by the manual. Removing the guard goes from 6 to 4 with gloves, a two-person lift and safety boots, and is the only step classed as PPE. Refitting the guard and testing moves from 10 to 5 with an interlock check and supervisor sign-off. No warnings appear, because every step ends below 15 and none gets worse.

Templates

The second template, Manual unloading, rates three steps for unloading a curtain-side lorry by hand at goods-in bay 3: securing the vehicle (10 to 5), opening the curtains (12 to 4) and moving boxes to pallets (12 to 6) using a roller conveyor and team lifts for items over 20 kg. Each template opens as a separate document, and Save version keeps dated snapshots of each JSA.

Downloads

Print / PDF gives the full colour JSA, Word (.doc) a file to edit further, and Web page (.html) a standalone copy for an intranet page or an email attachment.

Limits

The 5 by 5 matrix and its bands are a common convention, not a legal standard; if your company uses a different matrix, follow that instead. Only one control type can be chosen per step, so a step that mixes engineering controls and PPE should be classed by its main control. The tool cannot see the work, does not know local rules and is not legal or safety advice. A competent person must review the JSA, and it must be read alongside permits, method statements and your lockout procedure.

Worked example

Conveyor belt change: 5 steps, isolation risk 4 × 5 = 20 (very high) reduced to 1 × 5 = 5 (medium); every step below 15 after controls.

Quick facts

Frequently asked questions

Is a JSA the same as a JHA?

Yes, for practical purposes. JHA is the term OSHA uses in publication 3071, JSA is common in industry, and in the UK the same work is often called a task-specific risk assessment.

How is the risk number worked out?

Likelihood times severity, each scored 1 to 5, gives 1 to 25. The printout colours 1-3 green, 4-7 yellow, 8-14 amber and 15-25 red, and shows the rule under the table.

Why does a step keep the same severity after controls?

Most controls make harm less likely rather than less serious. A conveyor that starts while a hand is inside still causes a severe injury, so the sample lowers likelihood and keeps severity at 5.

What does the PPE warning mean?

PPE is the last line of the hierarchy. If a step scores 15 or more before controls and its control type is PPE, the tool asks you to look for elimination, substitution, engineering or administrative controls first.

How do workers sign the JSA?

Press Print worker sign-off sheet. It prints the job name, site and JSA date, a short declaration and 14 blank rows for name, company, signature and date.

Can I use my own risk matrix?

The scores are fixed at 1 to 5 with the bands shown. If your company uses a 3 by 3 or 4 by 4 matrix, write your own rating into the controls text and follow your company procedure.