House Construction Cost Estimator
Enter each floor's built-up area and your local all-in rate to see the cost by element, material quantities, allowances and a stage-wise payment plan.
Runs in your browser. Your files never leave your device. See how to check
…
How to do it
- 1Enter floors
On Inputs, add each floor with its built-up area and choose square metres or square feet.
- 2Set your rate
Enter the local all-in rate per unit of area for a standard finish and pick the quality level.
- 3Set allowances
Adjust contingency, fees, escalation and tax to your case.
- 4Check the elements
On Elements, edit shares or give an element its own rate, then read Breakdown.
- 5Price materials
On Materials, enter local unit prices for cement, steel, sand, aggregate and bricks.
- 6Plan payments
On Payment plan, set the start date and stages, then print the estimate or save a scenario.
About this tool
Before you talk to a contractor or a bank, you need a realistic first number for building your house. Quantity surveyors start with an order-of-cost estimate: the floor area multiplied by a rate per square metre or square foot, split into elements so you can see where the money goes. This estimator works the same way. List each floor with its built-up area, enter the all-in rate per unit of area that builders in your town charge for a standard-quality house, and pick a quality level. The rate is split into elements: excavation and foundation, the reinforced concrete frame, brick or block walls, plaster, flooring and tiling, doors and windows, electrical work, plumbing and sanitary fittings, painting, roofing and waterproofing, the kitchen, the staircase, external works and site set-up. Finishing elements scale with quality, so moving from standard to premium raises the tiles, fittings and joinery but not the concrete. Every share and rate is editable, and any element can have its own rate per area or become a quantity times a unit price.
Allowances
On top of the construction cost the tool adds contingency for the unknowns, design and approval fees, price escalation per year until the middle of construction, and any tax on construction. Change each percentage to match your case; the breakdown tab shows the cost per element and group, its share and its cost per unit of area, plus the total per square metre and per square foot.
Materials
The materials tab estimates cement bags, reinforcement steel, sand, coarse aggregate, bricks, floor tiles and paint from per-square-metre rules of thumb for a reinforced concrete framed house, with a unit price for each so you can see the material bill. These factors are a common starting point in South Asia and similar markets and change with the design, the soil and the building code, so treat them as a ballpark until an engineer gives you real quantities.
Stage-wise payment plan
Builders are usually paid in stages. The plan lists each stage with its share of the total and its length in weeks, gives the amount and the date range from your start date, and draws a monthly cash flow chart. Rebuild the plan from your floors to get one slab stage per floor.
Keep and compare
Save scenarios such as standard against premium quality or two floor plans, print the estimate, export it as CSV, save JSON and undo any change. The figures are an order-of-cost estimate from the rates you enter. They are not a quotation, a bill of quantities or engineering advice.
Worked example
A two-storey house has a 120 square metre ground floor and a 110 square metre first floor, 230 square metres in all. Local builders quote about 950 per square metre for a standard finish, so the construction cost is 218,500, with the RCC frame at 22 percent (48,070) and the foundation at 10 percent (21,850). Adding 7.5 percent contingency (16,387.50), 6 percent fees (14,093.25) and one year of 4 percent escalation (9,959.23) gives 258,939.98, about 1,126 per square metre or 105 per square foot. Premium finishes raise the construction cost to about 261,763 and the total to about 310,210. The rule-of-thumb material list gives roughly 989 bags of cement, 9.2 tonnes of steel, 58 cubic metres of sand and 19,800 bricks. The seven-stage plan starting on 4 January 2027 runs 34 weeks to 29 August 2027.
Quick facts
- Category: Home & Life
- Works in your browser, no sign-up, no upload.
- Your input stays on your device.
- Available in English.
- Content last reviewed:
- Official source: RICS New Rules of Measurement NRM 1 (order of cost estimating and elemental cost planning)
Frequently asked questions
What rate per square foot or metre should I use?
Ask two or three local builders for their current all-in rate for a house like yours, or use rates published by a public works department, a quantity surveying institute or a builders' association in your area. Enter that as the base rate for standard quality.
What is included in built-up area?
Usually the covered area of each floor measured to the outside face of the walls, including stairs and wall thickness. Open terraces, balconies and car porches cost less per area, so list them as separate rows at an adjusted area.
Why does quality not change the concrete cost?
The structure is designed for loads, not looks, so its cost changes little between finishes. Tiles, doors, windows, fittings, kitchens and paint change a lot, so only those elements scale with quality. You can change which elements scale.
How accurate are the material quantities?
They are rules of thumb for a typical framed house and can be off by 20 percent or more. A structural design and a bill of quantities give the real figures; use these only for an early budget and price check.
How much contingency should I keep?
Many self-builders keep 5 to 10 percent for a well-defined design and more if the soil, design or prices are uncertain. Raise it if you have not done a soil test or the drawings are not final.
Can I use it for an extension?
Yes. Enter only the new floor area, remove elements that do not apply, such as the staircase, and add items like demolition or connecting to the existing structure as quantity rows.