FMEA Worksheet (Failure Mode and Effects Analysis)

Choose process or design FMEA, enter each step, failure mode, effect, cause and current controls, rate severity, occurrence and detection from 1 to 10, and the worksheet works out the RPN and the AIAG & VDA action priority, tracks recommended actions and their due dates, and re-scores the risk once an action is taken.

Runs in your browser. Your files never leave your device. See how to check

…

How to do it

  1. 1
    Set up

    Choose PFMEA or DFMEA and name the team.

  2. 2
    Failure modes

    Add the step, mode, effect, cause and controls.

  3. 3
    Rate

    Pick severity, occurrence and detection from 1 to 10.

  4. 4
    Act

    Give High rows an action, owner and date.

  5. 5
    Re-score

    Enter new ratings and print the worksheet.

About this tool

The FMEA Worksheet is a structured log for failure mode and effects analysis, the method that asks what can go wrong at each process step or design function, how bad it would be, how often it is likely to happen and how well current controls would catch it. At the top you choose between Process FMEA (PFMEA) and Design FMEA (DFMEA), name the process or product, list the team and set the RPN level at which rows are flagged, 100 by default. Each failure mode is one entry with the step or item, the failure mode itself, the effect, the cause, the current prevention and detection controls, and three ratings picked from 1 to 10. The worksheet multiplies severity, occurrence and detection into the risk priority number and, alongside it, looks up the action priority of High, Medium or Low from the table published in the 2019 AIAG & VDA handbook. That table weighs severity first, then occurrence, then detection, so a severity 9 failure with modest occurrence can be High even when its RPN looks unremarkable. Every row also holds a recommended action, the person responsible, a target date and a note of the action taken. When you enter new severity, occurrence or detection values after the action, the table shows a new RPN and a new action priority; any of the three left blank keeps its original rating for the re-scored figures. The table can be sorted by any column and searched with a free-text box, which keeps a worksheet with dozens of rows manageable.

Who this is for

Quality and manufacturing engineers preparing a PFMEA for a new line or a customer submission, design engineers reviewing a DFMEA before a design release, reliability teams in maintenance, and students learning how severity, occurrence and detection combine into a risk ranking.

How to use it

1. Pick the FMEA type and fill in the process or product and the team. 2. Add a failure mode for each step, with its effect, cause and controls. 3. Rate severity, occurrence and detection with your company's tables. 4. Assign actions with owners and target dates to the High rows first. 5. After each action, enter the new ratings and print the worksheet.

Stats, warnings and charts

A row of figures above the table counts the failure modes, the rows with action priority H, the rows at or above your RPN flag, the highest RPN and how many recommended actions have been closed. Three warnings appear when they apply: a severity of 9 or 10 with no recommended action, a High priority row with no responsible person, and an action whose target date has passed with nothing recorded as taken. The chart draws the original RPN and the new RPN side by side for each row, so the effect of the actions is visible at a glance. A summary groups the rows by process step with the count of failure modes, the maximum RPN and the number of High priorities in each step.

What the sample shows

The sample is a PFMEA for a bracket welding line with four failure modes. Weld missing on one tack point scores 9, 4 and 6 for an RPN of 216 and priority H. Porosity in the seam weld starts at 7, 5 and 7, an RPN of 245 and also H; a flow alarm has been fitted, and the re-scored 7, 2 and 4 gives a new RPN of 56 and priority L. Part loaded upside down is 150 and M, and thin paint film is 36 and L, with no action needed. Three of the four rows are at or above the RPN flag of 100, and one of three actions is closed.

Action dates and exports

Open actions with a target date appear in an FMEA actions list sorted by days remaining, with those due inside 14 days highlighted, and the list downloads as an .ics file for a calendar. The worksheet exports as CSV, which opens in Excel or any spreadsheet, prints as a report that can be saved as PDF, and backs up as JSON. You can keep several named worksheets, one per process or product, and the whole set is held in this browser's storage.

Limits

Ratings are only as good as the rating tables your team uses, and the tool does not supply severity, occurrence or detection scales of its own. The H, M and L action priorities are approximate example values, check against the AIAG & VDA FMEA Handbook (2019) action priority tables; borderline rows in particular should be checked against your copy of the handbook or your customer's requirements. Because the data lives on this device only, export a backup regularly. This worksheet supports a risk analysis; it is not engineering, safety or legal advice and does not replace a cross-functional review.

Worked example

Bracket welding PFMEA: 4 failure modes; tack weld RPN 216 (AP H); porosity 245 (H) re-scored to 56 (L) after the flow alarm; 3 rows at or above RPN 100.

Quick facts

Frequently asked questions

What is the difference between RPN and action priority?

RPN is severity times occurrence times detection, so a 9 and a 3 count equally. Action priority is a lookup that gives severity the most weight and ranks each row High, Medium or Low; the tool's lookup holds approximate example values, check against the AIAG & VDA FMEA Handbook (2019).

Where do the 1 to 10 ratings come from?

From your organisation's or customer's rating tables for severity, occurrence and detection. The worksheet records the numbers you choose and does the arithmetic and the priority lookup.

How do I record the risk after an action?

Fill in Action taken and the new severity, occurrence and detection. Any new rating you leave blank uses the original value, and the New RPN and New AP columns update straight away.

Can I use it for a design FMEA?

Yes. Switch the FMEA type to Design FMEA and use the first field for the item or function instead of a process step. The ratings, priorities and actions work the same way.

Does it export to Excel?

It exports a CSV file with every field and the calculated RPN and priority columns, which Excel and other spreadsheets open directly. Print / PDF report gives a formatted copy.

Is my FMEA uploaded anywhere?

No. Entries stay in this browser's local storage on this device. Use Backup (JSON) to keep a copy or move the worksheet to another computer.

Guides for this tool

Completely freeNo cost, no sign-up
Files stay privateEverything runs in your browser
Easy in your languageAvailable in many languages