Flexible Budget and Variance Report
Enter budgeted and actual units, revenue, variable and fixed budget lines with actual totals and materials standards, and get a flexible budget report with spending, volume and materials variances.
Runs in your browser. Your files never leave your device. See how to check
…
How to do it
- 1Enter volumes
Budgeted and actual units.
- 2Add revenue lines
Rate per unit.
- 3Add cost lines
Variable or fixed.
- 4Enter actuals
Totals for each line.
- 5Set material standards
Price and quantity.
- 6Read the report
Variances with F and U.
About this tool
Comparing actual results with the original budget is misleading when volume changes. If you sold ten percent more units than planned, costs will naturally be higher, and a plain budget-against-actual report will show large adverse cost variances that are really a sign of success. A flexible budget solves this by restating the budget at the actual volume. Revenue and variable costs are recalculated at the actual number of units using the budgeted rates, while fixed costs stay as planned. Comparing actual results with that flexed budget shows how well prices and spending were controlled, and comparing the flexed budget with the original static budget shows how much the change in volume alone was worth. This tool builds the full report. You enter the period, the budgeted units and the actual units, then each budget line with its type. For revenue and variable lines the budget figure is a rate per unit; for fixed lines it is a total. Next to each you enter the actual total. The report lists actual, spending variance, flexible budget, volume variance and static budget for every line and for profit, with F for favourable and U for unfavourable. Key figures show actual, flexible and static profit and the total variance against the static budget. A second table splits the direct materials variance into a price variance, from paying more or less per kilogram than standard, and a quantity variance, from using more or less material than the standard allows for actual output, with the working shown for each.
Who this is for
Management accountants, finance managers, small manufacturers, accounting students and anyone who reports monthly results against a budget.
Static and flexible budgets
The static budget is the plan set before the period at the expected volume. The flexible budget asks what the plan would have looked like had you known the real volume in advance.
Spending variances
Actual minus flexible budget for each line shows what happened to prices and efficiency. A cost line above its flexed amount is unfavourable; a revenue line above its flexed amount is favourable.
Volume variances
Flexible minus static budget isolates the effect of selling more or fewer units. Fixed lines have no volume variance, because the flexed and static amounts are the same.
Price and quantity for materials
The price variance is the actual price minus the standard price, times the actual quantity bought. The quantity variance is the actual quantity minus the standard quantity for the output achieved, times the standard price.
Reading F and U
Favourable does not always mean good. Cheaper materials can lead to more waste, and lower marketing spend may cost sales later. Look at related variances together.
Using the report
Investigate the largest variances first, ask the manager responsible for the explanation, and update next period's standards if the change is permanent.
Comparing scenarios
The built-in comparison runs the same budget at 9,000 units, so you can see how the flexible budget and the volume variance move when sales fall short of plan.
Limits
A learning and reporting aid, not accounting advice. Variance analysis depends on sensible standards, so review them before drawing conclusions.
Worked example
For March 2027 the static budget is 10,000 units and actual sales are 11,000 units. Static budget profit is 13,000, flexible budget profit is 23,000 and actual profit is 13,300, so the volume variance is 10,000 F and the profit spending variance 9,700 U. Materials cost 4.20 a kg against a standard of 4.00 for 22,000 kg, a price variance of 4,400 U, and the quantity variance is 0 because 22,000 kg is exactly the standard for 11,000 units.
Quick facts
- Category: Business & Work
- Works in your browser, no sign-up, no upload.
- Your input stays on your device.
- Available in English.
- Content last reviewed:
- Official source: Flexible budgeting and standard cost variances (management accounting)
Frequently asked questions
What is a flexible budget?
The original budget restated at actual volume, with revenue and variable costs flexed and fixed costs unchanged.
What do F and U mean?
Favourable and unfavourable: whether a variance increases or reduces profit.
How do I enter fixed costs?
Choose Fixed as the type and enter the total budget for the period, not a rate.
What is a materials price variance?
The difference between actual and standard price per unit of material, times the actual quantity used.
Why is the quantity variance zero in the example?
Actual usage of 22,000 kg equals the standard of 2 kg for each of the 11,000 units made.
Is this accounting advice?
No. It is a learning and reporting aid.