Contractor Bid Comparison and Leveling Sheet
Put contractor quotes on a like-for-like basis: compare scope items, plug what is missing, adjust allowances and see the true leveled cost of each bid.
Runs in your browser. Your files never leave your device. See how to check
…
How to do it
- 1Define scope
List scope items for the first bid.
- 2Add bids
One scenario per contractor with the same item names.
- 3Mark status
Included, allowance or excluded.
- 4Adjust
Add allowance or risk adjustments.
- 5Compare
Read leveled totals side by side.
- 6Decide
Print the sheet with notes.
About this tool
When three builders quote for the same job, the cheapest headline price is often not the cheapest job: one leaves out skip hire, another uses a low allowance for the kitchen and a third assumes someone else does the decorating. Bid leveling puts the quotes on the same basis. Enter each contractor's bid as a scenario with their name, programme length in weeks, quote validity date and a quality or references rating, then list the scope items using the same item names in every bid. Mark each item as included, an allowance or excluded and enter its amount. The first bid is the benchmark: any scope item it includes that a later bid omits or excludes is plugged at the first bid's price so totals compare like for like, and you can add a further adjustment, for example to bring a low allowance up to the same level. Each bid shows its headline total, leveled total, number of missing items plugged, allowances, programme, quality rating and difference from the first bid. The scope table lists every item, the plugs and the leveled total, and notes record each bidder's qualifications and exclusions. Compare all bids side by side and print the leveling sheet for your decision or client.
Who this is for
Homeowners comparing builders' quotes, project managers, quantity surveyors, facility managers and anyone choosing between contractors.
Steps in leveling
| Step | What to do | |---|---| | Common scope list | Break the job into the same items for every bid | | Exclusions | Note what each contractor leaves out | | Plugs | Price missing items from another bid or an estimate | | Allowances | Bring provisional sums to the same level | | Qualifications | Read assumptions, validity and payment terms | | Non-price factors | Programme, quality, references, insurance |
Allowances
An allowance, or provisional sum, is a placeholder for something not yet specified, such as a kitchen. A bid with a lower allowance looks cheaper but simply moves the cost to later. Adjust allowances to the same level before comparing.
Beyond price
A slightly dearer bid from a contractor with better references, a realistic programme and clear terms is often better value. Record ratings and notes alongside the numbers.
Worked example
Alpha bids 114,500 with everything included. Beta's headline is 102,800, but it excludes skip hire (plugged at 2,100) and has a kitchen allowance 4,000 lower, so its leveled total is 108,900, still 5,600 below Alpha. Gamma bids 111,800 but leaves out decoration (plugged at 8,400), so its leveled total is 120,200, 5,700 above Alpha, though it has the best quality rating.
Limits
Leveling relies on consistent scope descriptions and fair plug values. Ask contractors to confirm missing items in writing. This is not legal or contractual advice. Data stays in your browser.
Worked example
Beta 102,800 headline → 108,900 leveled (skip hire plugged + kitchen allowance adjusted), 5,600 below Alpha.
Quick facts
- Category: Business & Work
- Works in your browser, no sign-up, no upload.
- Your input stays on your device.
- Available in English.
- Content last reviewed:
- Official source: Construction bid leveling (tender analysis) practice
Frequently asked questions
What is bid leveling?
Adjusting quotes so they cover the same scope, allowances and assumptions before comparing totals.
How are missing items priced?
At the first bid's price for that item; you can add other adjustments.
Why must item names match?
Items are matched by name across bids to find what is missing.
What about allowances?
Mark them as allowances and use the adjustment to bring them to the same level.
Can I include non-price factors?
Yes, programme length, quality rating and notes appear beside each bid.
Is it private?
Yes, data stays in this browser.