Construction Act Payment and Pay Less Notice Date Calculator
Enter each valuation and what happened; get the statutory dates, the notified sum, the sum due, default notice effects, interest and five draft notices.
Runs in your browser. Your files never leave your device. See how to check
…
How to do it
- 1Set the terms
Choose the Scheme or a contract preset, the part of the UK and the retention percentage.
- 2Add payment cycles
Add each valuation with its period end, application date, gross value to date and earlier payments.
- 3Record what happened
Enter the dates and amounts of any payment notice, pay less notice, default notice and payment.
- 4Read the dates
Open the dates tab for the due date, notice deadlines, final date, notified sum and sum due in each cycle.
- 5Draft a notice
Pick a cycle and a letter, fill in the parties and reasons, and print or download the notice.
- 6Keep the record
Print the payment timetable and export it as CSV for the project file.
About this tool
Payment disputes in construction are often lost on dates rather than on the value of the work. Under the Construction Act a payer who misses the deadline for a payment notice or a pay less notice can be bound to pay the full sum applied for, and a payee who never gives a default notice may find there is no notified sum at all. The periods are short, and the Act says that Christmas Day, Good Friday and bank holidays do not count, which catches people out every December. This calculator keeps a project's payment cycles in one table. For each valuation you enter the period end, the date of the application, the gross value to date and what was paid before, then the dates on which notices were actually given and money actually paid. It works out the due date, the latest date for the payer's payment notice, the latest date for a pay less notice and the final date for payment, moves the final date if the payee gave a default notice, and tells you the notified sum and the sum that had to be paid. It also flags late notices, short payment, late payment interest and the right to suspend, and drafts the notices.
The dates under the Scheme
Where a construction contract does not set out an adequate payment mechanism, the Scheme for Construction Contracts fills the gap. The payment due date is seven days after the end of the valuation period, or the date the payee makes a claim if later. The final date for payment is 17 days after the due date. The payer, or a specified person such as the contract administrator, must give a payment notice within five days of the due date stating the sum it considers due and how it is calculated. A pay less notice must be given no later than seven days before the final date. If the contract has its own compliant terms, choose a preset or type the contract's periods into the payment terms tab.
Default notices and suspension
If the payer gives no payment notice in time, the payee may give its own notice at any time afterwards, and the final date for payment moves back by the number of days between the missed deadline and the payee's notice. Some contracts say the application itself stands as the payee's notice; tick that option and no separate notice is needed. If the sum due is not paid by the final date, the payee may give at least seven days' notice of intention to suspend work and can claim statutory interest at 8% over base rate.
Worked example
Valuation 1 ends on 30 September 2026 with a gross value of £48,000; 3% retention is £1,440, so £46,560 is applied for. The due date is 7 October, the payment notice deadline 12 October, the pay less deadline 17 October and the final date 24 October, and it was paid on time. Valuation 2 had no payment notice by 12 November; the payee's default notice on 16 November moved the final date four days to 28 November, so a pay less notice given on 20 November for £41,000 was in time and £41,000 was due. Valuation 3 was paid six days late, giving interest of £105.04 at 11.75%. Valuation 4 ends on 18 December: because Christmas Day is not counted, its due date is 26 December, the payment notice is due by 2 January 2027 and the final date is 14 January 2027.
Limits
This is a date calculator and drafting aid, not legal advice. It does not decide whether a contract's own terms are compliant, whether a notice was validly served or what a reasonable basis of calculation is, and it does not cover adjudication. The base rate is an example: check the Bank of England rate for your dates, and take advice before suspending work.
Worked example
Valuation 2: default notice on 16 November moves the final date from 24 to 28 November, so the 20 November pay less notice for £41,000 is valid; Christmas pushes valuation 4's due date to 26 December.
Quick facts
- Category: Business & Work
- Works in your browser, no sign-up, no upload.
- Your input stays on your device.
- Available in English.
- Content last reviewed:
- Official source: Housing Grants, Construction and Regeneration Act 1996 Part II as amended by the Local Democracy, Economic Development and Construction Act 2009; Scheme for Construction Contracts (England and Wales) Regulations 1998
Frequently asked questions
Do weekends count in Construction Act periods?
Yes. Only Christmas Day, Good Friday and bank holidays in the part of the UK where the work is are left out (section 116). Choose England and Wales, Scotland or Northern Ireland for the right bank holidays.
What is the notified sum?
The sum in a valid payment notice from the payer, or in the payee's default notice or application where that stands as the notice. It is what must be paid by the final date unless a valid pay less notice reduces it.
What happens if a pay less notice is late?
It has no effect, and the full notified sum must be paid by the final date. The payer can still argue about the value in a later valuation or in adjudication.
Does a default notice change the final date?
Yes. The final date for payment is postponed by the number of days between the date the payer's notice was required and the date the payee's notice is given.
Can I use this for JCT or NEC contracts?
Yes. Choose a preset or enter the contract's own periods for the due date, final date, payment notice and pay less notice. Read the contract to confirm them.
What interest can I claim for late payment?
Unless the contract gives a substantial remedy, the Late Payment of Commercial Debts (Interest) Act 1998 allows 8% over the Bank of England base rate plus fixed compensation of £40, £70 or £100 depending on the debt.