How to Build a Long-Range Training Calendar Without Double-Booking Your People
A step-by-step way to plan a unit's training year: fixed points first, consistent sub-unit names, event status, clash checks and quarterly calendars.

How to Build a Long-Range Training Calendar Without Double-Booking Your People
The long-range training calendar is one of those documents everybody relies on and nobody quite trusts. It starts as a tidy plan at the beginning of the training year, and by the second quarter it is full of events nobody resourced, clashes nobody noticed and leave blocks that landed on top of a range. Most of that can be avoided with a little structure at the start.
Put the fixed points in first
Start with what you cannot move: block leave, higher headquarters inspections, ceremonies, exercises set by the formation, and range or training area slots you have already been allocated. Everything else fits around them. Planning the flexible events first and then discovering the leave block lands on top of them is the most common way a calendar falls apart.
Name who takes part, consistently
For every event, record who attends. Use a short, fixed set of names: "All", "HQ", "1 Platoon", "2 Platoon" and so on. If one planner writes "1 Pl" and another writes "First Platoon", no tool or person will spot that they are the same people. The word "All" matters too: an event for the whole unit clashes with anything else happening on the same days.
Give every event a status
A status tells everyone how firm an event is. A simple ladder works well: Proposed, Locked in once the commander agrees, Resourced once ammunition, transport, instructors and the training area are confirmed, then Done. Cancelled events stay on the list for the record but drop out of every count. At each planning meeting, the events still at Proposed or Locked in are the agenda.
A worked example
A company plans November. The range for All runs from 10 to 12 November, three days, and is locked in. 1 Platoon proposes a land navigation day on 11 November. Because the range involves All, and 1 Platoon is part of All, both events show a clash. The fix is either to move land navigation to 13 November or to change the range to exclude 1 Platoon for that day. Block leave from 19 December to 3 January is set for All; anything else for the same dates will clash with it.
In Q4 2026 that gives three events and 20 committed days: 3 for the range, 1 for navigation and 16 for block leave. Note that leave counts as committed time, not training. If your headline figure should show training only, keep leave in a separate log or subtract it.
Look a quarter at a time
A full year on one page is hard to read. Group events by quarter and print each quarter as its own sheet with dates, event, who, type, location, lead and status. Pinned on a wall or sent ahead of a planning conference, a quarterly sheet invites corrections in a way a 60-row spreadsheet never does.
Common mistakes
- Leaving end dates blank or wrong, so multi-day events look like single days.
- Using inconsistent sub-unit names, which hides real clashes.
- Locking in events without listing resources, then finding the vehicles are already booked.
- Forgetting that a whole-unit event blocks every sub-unit.
- Never closing events as Done, so the calendar no longer shows what actually happened.
Review rhythm
Hold a short planning review every few weeks: clear clashes, move events up the status ladder and print the next quarter. Share the upcoming events with everyone's calendar so dates are seen early. When a higher headquarters moves one of your fixed points, update it the same day and rerun the clash check, because a single moved inspection can ripple through a whole quarter.
This is general planning guidance, not official direction or legal advice; your unit's approved training programme is the authority.
Using the Unit Training Calendar and Long-Range Planner
The shobfree.com planner runs in your browser and nothing is uploaded. Type your unit's name in Settings, then add each event with start and end dates, who takes part, its type, location, lead, status and resources. Clashes appear in the Conflicts with column and as notes above the table. The Board tab moves events between statuses, the Summary tab prints a calendar for each quarter, and upcoming events export to any calendar app as an .ics file. Keep a CSV export or JSON backup, and use separate logs for a draft and an approved plan.