Small Business

How to Carry Out a Time Study and Set a Standard Time

A practical guide to stopwatch time study: breaking jobs into elements, timing cycles, rating, allowances and turning it all into output per hour.

Saizul Amin
Saizul Amin19 Nov 2026 · 4 min read
How to Carry Out a Time Study and Set a Standard Time

Knowing how long a job should take sits behind almost every planning decision in a workshop or factory: how many people a line needs, what to quote a customer, whether a bonus scheme is fair and whether a new method is really quicker. Stopwatch time study is the traditional way to find out. This guide explains the steps and shows how the free Time Study and Work Measurement Sheet handles the arithmetic while you watch the job.

Before you start the watch

A time study measures one method under one set of conditions, so write those down first: the operation, the tools and jigs, the material, the workplace layout and the operator. Choose an operator who is trained and experienced in the method, explain what you are doing and why, and make sure the method is the agreed one. Timing a job that is still being worked out wastes everyone's effort.

Break the job into elements

An element is a distinct part of the job with a clear start and end, called a break point. Good break points are things you can hear or see, such as a part dropping into a box or a drill reaching its stop. Keep elements short enough to time accurately but long enough to read, usually a few seconds or more.

Separate the types. Repetitive elements happen every cycle. Occasional elements happen now and then, such as changing a full box every ten parts; give them a frequency like 1/10. Machine-controlled elements run at a speed set by the machine, so the operator's pace does not affect them.

Time the cycles

There are two ways to read a stopwatch. With snapback timing the watch returns to zero at every break point, so each reading is one element. With continuous timing the watch keeps running and you write down the total at each break point, then subtract. Continuous timing is more accurate because no time is lost between readings, but it needs more arithmetic. The sheet does that subtraction for you.

On the sheet, press Start and then tap the large button, or the space bar, at the end of each element. Press S to skip an occasional element that did not happen in that cycle. The readings drop into the grid as you go, and you can type corrections afterwards.

Deal with abnormal readings

Sometimes a reading is clearly wrong: the operator dropped a part, someone asked a question, or you missed a break point. Mark such readings as excluded and note why. The sheet can also flag readings automatically if they are more than a set percentage away from the element's median, but always check them yourself rather than letting a rule decide.

Rate the performance

People work at different speeds, so raw times are not a standard. While timing, the observer judges the pace of each element against a standard rating. On the BS 100 scale, 100 is the pace a qualified worker can keep up over a working day without undue fatigue. If an element is done at what you judge to be rating 110, its basic time is the observed time multiplied by 110 and divided by 100. Rating takes practice, and observers should train on films of known pace.

Add allowances

Nobody can work continuously for a full shift. Relaxation allowances cover personal needs and recovery from fatigue, and contingency allowances cover small unavoidable delays. They are usually added as a percentage of basic time. The tool includes an example table in the style of the ILO tables, but these are only illustrations: use the allowances agreed in your organisation, and record their source.

From basic time to output

Standard time for each element is basic time plus allowances. Multiply by the frequency, add the elements, and you have the standard time per unit. In the sample bench drilling study, four elements over six cycles give 32.51 seconds per part. That is 3,600 ÷ 32.51 = 110.7 parts per hour, or about 830 parts in a 450-minute shift.

The same figure lets you measure performance later. If an operator makes 100 parts in 60 minutes, the standard minutes produced are 100 × 32.51 ÷ 60 = 54.2, and performance is 54.2 ÷ 60 = 90% of standard.

Have you timed enough cycles?

Variable elements need more readings. A common estimate from Niebel's textbook is n′ = (40 √(nΣx² − (Σx)²) ÷ Σx)² for 95% confidence and ±5% accuracy. The sheet calculates it for each element and warns when the most variable one needs more cycles than you have timed.

Keep it fair and current

A standard time is only valid for the method and conditions studied. When the method, tooling or material changes, study the job again. Share the results with the people affected and keep the printed study sheet with its signatures; it is a record of how the standard was set, not a judgement of the person who was timed.