How to Plan a Sprint with Story Points, Capacity and a Burndown Chart

Sprint planning in practice: ranking the backlog, estimating in points, forecasting capacity from velocity and reading burndown and velocity charts.

Saizul Amin
Saizul Amin2 Nov 2026 · 4 min read
How to Plan a Sprint with Story Points, Capacity and a Burndown Chart

How to Plan a Sprint with Story Points, Capacity and a Burndown Chart

Sprint planning goes wrong in two familiar ways. Either the team commits to everything the product owner wants and misses half of it, or it plans so cautiously that the sprint goal means nothing. Good planning sits in between, and it rests on three simple ideas: a ranked backlog, a capacity forecast based on what the team actually finished before, and a daily check on whether the sprint is on track. This guide walks through each idea using the free sprint planner and scrum board.

Start with a ranked backlog

The product backlog is a list, not a pile. The most valuable and best understood items sit at the top, and the vague ideas sink to the bottom. Before planning, the product owner moves items up and down until the order reflects what matters now. Each item gets a type (story, bug, task or spike), a short title that a newcomer could understand and an epic so related work stays together.

Estimate in story points

Story points describe size relative to other items, not hours. A 5-point story is roughly twice the work of a 3-point story, with some allowance for uncertainty. Most teams use a modified Fibonacci scale: 1, 2, 3, 5, 8, 13, 20 and 40. The gaps grow with size because bigger items carry more unknowns. If an item is 20 or more, it is usually worth splitting before a sprint starts. Planning poker is a good way to agree on points as a team.

Forecast capacity from velocity

Velocity is the number of points a team completes in a sprint. One sprint tells you little; the average of the last three is a much better guide. Capacity then adjusts that average for the coming sprint. If two of five people are away for half the sprint, the team has 80 % of its usual person-days, so it should plan about 80 % of its usual velocity. The planner does this automatically: it divides available person-days by nominal person-days and multiplies the result by the three-sprint average.

There is also a focus factor per person. Nobody spends eight hours a day on sprint work; meetings, support and reviews take their share. A focus of 60 to 70 % is common. The planner turns this into focus hours, which helps teams that also plan tasks in hours.

Plan the sprint

With the forecast in view, pull items from the top of the backlog into the sprint until the planned points match it. Write a sprint goal that explains why these items belong together, for example "Customers can pay by card at checkout". If the plan exceeds the forecast, the planner shows a warning with the number of points to move back. It is better to finish a smaller plan and pull more work later than to carry half-done items into the next sprint.

Work the board

During the sprint, cards move from To do through In progress and Review to Done. Swimlanes make problems visible. Grouping by assignee shows when one person holds four items in progress at once; grouping by epic shows whether the sprint goal is advancing or only side work is moving. Limiting work in progress, finishing before starting, is the single most useful board habit.

Read the burndown

The burndown chart plots remaining points for each working day. The dashed ideal line runs from the starting scope to zero. If the remaining line stays flat for several days, work is stuck, often in review. A separate scope line rises when items are added mid-sprint. Without it, added work looks like slow progress; with it, the team can discuss the real cause in the retrospective.

Learn from velocity

When you close a sprint, the planner records committed and completed points. The velocity chart compares them sprint by sprint, and the say/do ratio shows how reliable the plans have been. A team that completes 85 to 100 % of its commitment most of the time plans well. Large swings suggest unclear stories, hidden work or too much unplanned support.

A short example

A team averages 21, 24 and 23 points over the last three sprints, so its velocity is about 22.7. In the next ten-day sprint, one member has two days off, leaving 28 of 30 person-days. The forecast is 22.7 × 28 ÷ 30, roughly 21 points. The product owner wants 26 points of work, so the team moves a 5-point story back and agrees a clear goal for the remaining 21.

Limits

Velocity measures a team's own pace and should never be compared across teams or used to rate individuals. Story points are not hours and do not convert reliably. The planner keeps its data in one browser; share the exported CSV or report with the team rather than expecting live sync.