How to Read a Sprint Burndown Chart and Make One in Minutes
What the ideal, actual and scope lines mean, how to log a sprint day by day, a worked 42-point example and the burndown mistakes teams repeat.

How to Read a Sprint Burndown Chart and Make One in Minutes
A burndown chart answers one question every day of a sprint: are we going to finish what we promised? It is simple to draw, yet teams often get it wrong by logging the wrong numbers or reading the shape badly. The Sprint Burndown Chart Maker builds the chart from a short daily log, and this guide covers how to use it well.
The three lines
- Ideal. A straight line from the committed points on day one to zero on the last day. It assumes the same amount of work is finished every day.
- Actual. The points still remaining at the end of each day.
- Scope. The total size of the sprint, which moves when work is added or removed.
Without the scope line, a flat stretch is ambiguous. Did the team stall, or did someone add work? With it, you can tell at a glance.
What to log each day
For each working day, enter two numbers: the points completed and any change in scope. Added work is positive, removed work is negative. Count a story as completed only when it meets the team's definition of done. Half-finished work counts as zero, which feels harsh but keeps the chart honest.
Leave out weekends and holidays. The ideal line divides work evenly across the days you list, so a Saturday in the list makes the line slope too gently.
A worked example
The default is Sprint 24: 42 points committed across ten working days.
| Day | Done | Scope change | Remaining |
|---|---|---|---|
| Mon 1 | 0 | 0 | 42 |
| Tue 2 | 5 | 0 | 37 |
| Wed 3 | 3 | +3 | 37 |
| Thu 4 | 6 | 0 | 31 |
| Fri 5 | 2 | 0 | 29 |
| Mon 6 | 8 | 0 | 21 |
| Tue 7 | 4 | -2 | 15 |
| Wed 8 | 5 | 0 | 10 |
After eight days, 33 points are done and 10 remain. The sprint grew by a net 1 point. The team averaged about 4.1 points a day, but finishing in two days needs 5 a day, so the verdict is behind. The actual line sits at 10 while the ideal line is at about 9.3, close but slipping.
This is the moment the chart is most useful. With two days left the team can talk honestly about which story to drop rather than discovering on the last afternoon that two are unfinished.
Reading common shapes
Flat, then a cliff. Little progress for days, then a big drop. Stories are too large, so nothing is "done" until the end. Split them.
Rising line. Scope is growing faster than delivery. Protect the sprint or move new work to the backlog.
Ends above zero, sprint after sprint. The team commits to more than its velocity supports. Use the average from the last three sprints when planning.
Perfect diagonal every time. Lovely, but check whether people are logging what they expect rather than what is done.
Sharing the chart
The tool offers two downloads. Chart as SVG produces a clean image titled with the sprint name that drops straight into slides for the review or retrospective. Data CSV keeps the daily numbers for a spreadsheet or for tracking velocity over many sprints.
You can add a tab for each sprint and use Compare all to see remaining points, velocity and needed pace side by side. Over several sprints, that comparison is the honest basis for planning: if the team has averaged around 38 points, committing to 42 again is a choice to start behind.
Common mistakes
Logging partial credit. It makes the line look smoother and hides the real risk.
Not recording scope changes. If new work is quietly absorbed, the burndown looks like poor performance.
Using it to judge individuals. A burndown measures the team's flow of work, not effort. Using it as a score encourages gaming.
Updating once a week. The chart is useful only if it is current, ideally right after stand-up.
Keep it simple