Running a SMED Workshop: Cutting Changeover Time Step by Step
A practical SMED guide: filming a changeover, separating internal and external work, converting and streamlining steps and measuring the hours you free up.

Long changeovers push factories towards big batches. If it takes over an hour to swap a mould, nobody wants to do it twice a shift, so stock builds up, lead times stretch and urgent orders wait. Single-Minute Exchange of Die, usually shortened to SMED, attacks the cause. It is the method Shigeo Shingo refined in the 1950s and 1960s to bring press changeovers down from hours to minutes, and it still works on presses, moulding machines, packing lines, printing presses and CNC cells today.
Start with a real changeover
A SMED study begins on the shop floor, not in a meeting room. Pick one machine and one common product change, and watch it from the last good part of the old run to the first good part of the new one. Film it if you can, with the team's agreement, because the video settles arguments later. Record every step with its start and end time: walking to the store, searching for a spanner, waiting for the forklift, unclamping, cleaning, adjusting, making trial shots, waiting for quality to sign off.
Most teams are surprised by the first list. A changeover everybody thought took 40 minutes often takes 70, and a large part of it is walking, searching and waiting rather than technical work.
Separate internal and external work
The core idea of SMED is the distinction between internal and external work. Internal work can only be done while the machine is stopped: removing the old die, fitting the new one. External work could be done while the machine is still running the previous order: fetching the next die, pre-heating it, finding the right tools, preparing paperwork. In a first study, external work done during the stop is common, and simply moving it outside the stop with a checklist and a staging area can cut downtime by a third or more without spending money.
Mark each recorded step as internal or external, then ask of every internal step whether it really needs the machine stopped.
Convert internal work to external
The second stage changes the method so that internal steps become external. A mould that is pre-heated on a trolley no longer needs heating in the press. A die that arrives on a transfer cart at the right height no longer needs a crane during the stop. A duplicate fixture set up off-line can be swapped in a minute. These changes need some engineering effort but pay back quickly on machines that change over many times a week.
Streamline what remains
Third, streamline the internal steps that must stay. Replace bolts with quick clamps or quarter-turn fasteners, standardise clamp heights, fit locating pins so the die drops into position, colour-code and quick-couple water and air lines, and store machine settings per product so the first shot is close to right. Adjustment and trial runs are often the biggest internal loss after searching, and they shrink dramatically once the set-up is repeatable. Where two people are available, some steps can run in parallel: one purges the barrel while the other mounts the mould.
Measure the result
Compare the before and after properly. Downtime is the sum of internal time; external time still counts as work but does not stop the machine. A Gantt-style chart of the stop makes the change visible to everyone, and a Pareto of internal time by category shows where to look next. Then turn the saving into something managers notice: minutes saved per changeover, times changeovers a week, times working weeks, gives machine hours freed a year. Multiply by your cost of a machine hour, or better, show the extra output or the smaller batch sizes the time allows.
In one moulding example, a 72-minute stop fell to 20 minutes after converting mould fetching and pre-heating, eliminating the tool search with a shadow board and streamlining clamping and trials. At six changeovers a week that freed nearly 250 machine hours a year.
Keeping the gains
Changeover improvements fade unless the new method becomes standard work. Write a one-page changeover sheet with the new sequence, put the external checklist where the team leader sees it, and re-time a changeover every few weeks. The SMED Changeover Analysis Tool has a lap stopwatch for timing, a plan column for each step and a button to start a follow-up study from the improved state, so the second and third rounds take less effort than the first.
A final word on safety: every new method, especially around heavy dies, hot moulds and stored energy, needs a risk assessment before it is used. SMED is about removing waste, never about rushing.