Purchase Requisition Forms: What to Include and How to Approve
What a purchase requisition is, how it differs from a purchase order, what to write in it, how to check the budget and who should approve which amounts.

Every organisation that buys things needs a moment between "we need this" and "we ordered it". That moment is the purchase requisition: an internal request that explains what is needed, why, how much it will roughly cost and which budget pays, so that the right person can approve it before anyone commits money.
Requisition or purchase order?
The two documents are often confused.
- A purchase requisition is internal. A department sends it to management or purchasing. Prices are estimates, and suppliers are suggestions.
- A purchase order goes to the supplier. It has agreed prices, delivery terms and payment terms, and it is a commitment to buy.
The requisition comes first. Once it is approved, purchasing raises the order, often after collecting quotes.
What to put in a requisition
A number and dates. A unique number such as PR-2026-0042, the request date and the date the items are needed by.
Who is asking. Name, email, department and the cost centre or project code.
Where it goes. The delivery location, so goods do not end up at reception.
Why. A short purpose and justification. This is the part approvers read first, so make it specific: "Replace three failing support laptops" is better than "IT equipment".
What. One line per item with a clear description, a specification, quantity, unit, estimated unit cost and, if known, a suggested supplier.
How much. Subtotal, tax, delivery and the estimated total, with the total in words if your policy asks for it.
Which budget. The budget head and account code, with the amount allocated, already spent and already committed.
Priority. Normal, urgent or critical, so purchasing can plan.
Quotes and notes. Supplier quotes received and anything the buyer should know.
Checking the budget
A requisition should never come as a surprise to the budget holder. The check is simple:
Available = allocated − spent − committed
If the IT equipment budget is 12,000, with 4,300 spent and 1,250 committed to open orders, 6,450 is available. A request of 2,850 leaves 3,600 and uses 70 % of the budget. If the balance after the request would be negative, the request needs a budget transfer or a smaller scope.
Remember to count approved requisitions that have not yet been invoiced as committed, otherwise two requests can spend the same money.
Who approves what
Approval limits keep small purchases fast and large ones controlled. A typical chain:
- Department head: any amount
- Finance manager: from 1,000
- Director: from 10,000
A request of 800 needs one signature; 2,850 needs two; 12,000 needs three. The Purchase Requisition Form Maker applies these levels for you and puts a signature box for each required approver on the PDF.
Step by step with the form maker
- Set up your company name, currency, logo, paper size and numbering pattern, for example PR-{YYYY}-####.
- Enter your approval levels and their starting amounts.
- Press New requisition. The number and dates are filled in.
- Describe the need: requester, department, cost centre, delivery place, priority and purpose.
- Add the items with quantities and estimated costs.
- Enter the budget figures and check the balance after the request.
- Download the PDF, collect signatures, and update the status as the request moves from submitted to approved, ordered and closed.
Keeping a register
All requisitions stay in your browser, listed with their status. Filter by status to see what is waiting for approval, export the register as a CSV for a monthly report, and save a backup file to keep a copy or move to another computer.
The form maker does not replace an accounting system; the budget figures are the ones you enter. For a small team, though, a clear numbered form and a simple register already solve most "who approved this?" questions.