Earned Value Management Explained: Track Project Cost and Schedule
A clear guide to earned value: PV, EV and AC, CPI and SPI, forecasts such as EAC and TCPI, earned schedule and how to report project status honestly.
Earned Value Management Explained: Track Project Cost and Schedule
"We have spent 45 % of the budget" sounds like a status report, but on its own it says nothing about whether the project is healthy. Spending 45 % while finishing 60 % of the work is excellent; spending 45 % while finishing 20 % is a crisis. Earned value management (EVM) is the standard way to connect money and progress. This guide explains the core numbers and how to use them with the free project budget and earned value tracker.
The three base numbers
At any status date, EVM compares three values, all in money:
- Planned value (PV): the budget for the work that should have been done by now according to the plan.
- Earned value (EV): the budget for the work that has actually been done. If a task with a 10,000 budget is 40 % complete, it has earned 4,000.
- Actual cost (AC): what has really been spent on that work.
The total budget is called the budget at completion (BAC).
Variances and indices
From those three numbers come two variances and two indices:
- Cost variance, CV = EV − AC. Negative means you paid more than the work was worth.
- Schedule variance, SV = EV − PV. Negative means less work is done than planned.
- Cost performance index, CPI = EV ÷ AC. A CPI of 0.89 means each unit of money buys 0.89 units of planned work.
- Schedule performance index, SPI = EV ÷ PV. An SPI of 0.80 means the project is progressing at 80 % of the planned rate.
Indices are easier to compare across projects than variances, because they are ratios. A common rule of thumb treats values above 0.95 as healthy, 0.90 to 0.95 as a warning and below 0.90 as needing action.
Forecasting the final cost
The most used forecast is the estimate at completion, EAC = BAC ÷ CPI. It assumes the cost efficiency so far will continue, which in practice often proves optimistic rather than pessimistic. Two alternatives are useful:
- AC + (BAC − EV) if the overrun was a one-off and the rest will go to plan.
- AC + (BAC − EV) ÷ (CPI × SPI) when being late also drives cost, for example through extended staff time.
From EAC follow the estimate to complete (ETC = EAC − AC) and the variance at completion (VAC = BAC − EAC).
The to-complete performance index
TCPI = (BAC − EV) ÷ (BAC − AC) is the cost efficiency you would need on the remaining work to finish exactly on budget. If it is 1.09 while your CPI so far is 0.89, finishing on budget would require a sudden 20 % improvement. That is the moment to talk to the sponsor about a new budget rather than hope.
Earned schedule
Classic SPI has a known flaw: when a late project finally finishes, all work has been earned, so EV equals PV and SPI returns to 1.00. Earned schedule, introduced by Walt Lipke, measures schedule in time instead of money. It finds the date at which the plan expected today's earned value; the time between project start and that date is the earned schedule (ES). SPI(t) = ES ÷ actual time stays meaningful to the end, and the planned duration divided by SPI(t) gives a forecast finish date.
Measuring percent complete honestly
EVM is only as good as the progress figures. Optimistic estimates such as "90 % done" for weeks are common. Better rules:
- For short tasks, use 0/100 (not started or finished) or 0/50/100.
- For longer tasks, use milestones with agreed weights.
- For repetitive work, count units: metres laid, tests passed, rooms finished.
Setting it up step by step
- List tasks with budgets and planned start and end dates.
- At each reporting date, set percent complete for each task.
- Log actual costs with dates as invoices and timesheets arrive.
- Read the dashboard and the S-curve, where PV, EV and AC are plotted over time.
- Explain the biggest variances task by task in your report.
Reading the S-curve
When the EV line sits below the PV line, the project is behind schedule. When the AC line sits above the EV line, it is over budget. Both together, with the gap widening, is the classic pattern of a project in trouble, and the earlier it is spotted the cheaper it is to fix.
Limits
Earned value is a measurement method, not a guarantee; forecasts extrapolate past performance and can be wrong when circumstances change. This tracker spreads planned value evenly over calendar days and does not model resource loading, working calendars or contract rules. It is not accounting, audit or contractual advice.