Prepare and issue permits to work with hazards, controls, gas tests and sign-offs for hot work, height, confined space, isolation and excavation jobs.

Saizul Amin
Saizul Amin5 Nov 2026 · 4 min read
How to Use a Permit to Work for Hot Work, Height and Confined Spaces

Some jobs on a site, in a factory or in a building are dangerous enough that a quick word before starting is not sufficient. Welding next to a fuel line, working on a roof edge, climbing into a tank, opening an electrical panel or digging near buried cables have all killed people who were in a hurry. A permit to work is the written system that slows such jobs down just enough to make them safe.

This guide explains how a permit system works and how to prepare and run permits with a simple tool.

What a permit does

A permit is a formal agreement between two people. The issuer, sometimes called the area authority, controls the place where the work happens. The receiver, or performing authority, leads the people doing the work. Together they record what the job is, where and when it happens, who is doing it, what the hazards are and what controls are in place. Work can only start when the issuer signs, and the area only goes back to normal use when the issuer accepts it back at closure.

Permits are for non-routine, high-risk work. Routine tasks covered by ordinary procedures do not need them.

Choose the right template

Open the Permit to Work Form Maker and start a new permit from a template: hot work, work at height, confined space entry, electrical isolation with lockout and tagout, excavation, or general cold work. Each template has sections for preparation, hazards, controls, protective equipment, tests and closure. You can edit any template to add your site's own checks.

Fill the header

Give the permit a number and record the site, the location or equipment and a clear description of the work. Set the date and the valid-from and valid-until times. Name the issuer, the receiver and every worker covered. Name the fire watch, standby person or confined space attendant. Record gas test results with the time and the person who tested, isolation details with lock and tag numbers, any linked permits and the emergency contact and rescue plan.

Confirm each check on site

Walk the job together. For each line, mark Confirmed, Not OK or N/A, and add notes or photos. For hot work, that means moving or covering combustibles within about eleven metres, testing for flammable gas, placing extinguishers and naming a fire watch for the work and at least an hour afterwards. For height, it means asking first whether the work can be done from the ground, then checking scaffold tags, edge protection, harnesses and anchors and the rescue plan. For confined spaces, it means blanking lines, ventilating, testing the air at three levels and posting an attendant who never goes in. For electrical work, it means locking off every energy source with a personal lock for each worker and proving the equipment dead.

Anything marked Not OK gets a severity, and stop-work items must be fixed before work starts.

Display the permit

Print the one-page site permit and post it at the job. It shows the number, validity, people, gas tests, every check with its status and a sign-off table for issue, extension and closure. While any check is open or not OK, the printout states that the permit is not valid, so nobody can mistake a half-finished form for permission to start.

If conditions change, an alarm sounds or a control fails, the work stops and the permit is suspended until the issuer reviews it.

Close it properly

Closure is where many permit systems fail. When the work is done, or stopped for the day, the receiver confirms that tools and waste are removed, isolations are removed only by the people who applied them, guards and barriers are back, and the area is safe. For hot work, the fire watch checks the area again after thirty and sixty minutes. The issuer inspects and signs to accept the area back, and the permit is filed.

Keep closed permits for as long as your procedure or regulator requires. These templates are a starting point for your own system, not a replacement for your site's procedure, a competent risk assessment or the law where you work.