OEE Explained: Availability, Performance, Quality and the Six Big Losses
How to calculate overall equipment effectiveness, what a good OEE is, how to find the six big losses and how to use OEE for capacity planning.

OEE Explained: Availability, Performance, Quality and the Six Big Losses
Machines rarely produce as much as their nameplate suggests. Overall equipment effectiveness (OEE) shows how much of the planned time actually turns into good parts at full speed, and where the rest goes. The OEE Calculator computes it and the losses in parts. This guide explains the method and how to use it.
The three factors
Availability = run time / planned production time Planned production time is the time the machine is scheduled to run. Run time subtracts unplanned stops and changeovers.
Performance = (ideal cycle time × total count) / run time It compares what was made with what could have been made at the ideal speed during the run time. Small stops and slow cycles reduce it.
Quality = good count / total count Scrap and rework, including start-up rejects, reduce it.
OEE = availability × performance × quality, which also equals good parts × ideal cycle time / planned time.
A worked example
A shift of 420 planned minutes has 47 minutes of stops, so the run time is 373 minutes. The ideal cycle is 1.0 second. The machine made 19,271 parts, of which 18,848 were good.
- Availability: 373 / 420 = 88.8 %
- Performance: 19,271 s / 22,380 s = 86.1 %
- Quality: 18,848 / 19,271 = 97.8 %
- OEE: 74.8 %
At the ideal rate, the shift could have made 25,200 good parts. 2,820 were lost to stops, 3,109 to speed losses and 423 to rejects.
The six big losses
Total productive maintenance (TPM) groups losses into six categories:
- Breakdowns (availability)
- Setups and adjustments (availability)
- Small stops and idling (performance)
- Reduced speed (performance)
- Start-up rejects (quality)
- Production rejects (quality)
Small stops are often the biggest surprise: dozens of 30-second jams per shift add up but rarely appear in maintenance records.
What is a good OEE?
- 85 %: often called world class for discrete manufacturing, made up of 90 % availability, 95 % performance and 99.9 % quality.
- 60 %: typical for many plants.
- 40 %: common when a plant first starts measuring.
Compare your own machines and trends rather than chasing a universal number.
Pitfalls
- Wrong ideal cycle time: using a comfortable standard instead of the true best cycle inflates performance. If performance exceeds 100 %, the ideal is wrong.
- Hiding losses in planned time: excluding changeovers or meetings from planned time flatters availability.
- Averaging across machines: a bottleneck's OEE matters more than the plant average.
- Using OEE as a target for operators: it is a tool for finding losses, not for blaming people.
Improving OEE
- Availability: preventive and autonomous maintenance, SMED for quick changeovers.
- Performance: root-cause analysis of small stops, better material feeding, speed optimisation.
- Quality: poka-yoke, standard work and stable start-up procedures.
Capacity planning
Machine hours needed = demand × ideal cycle time / OEE. For 50,000 parts a week at 1 second each and 75 % OEE, you need 18.5 hours. With two 8-hour shifts over five days, one machine is enough at 23 % utilisation. Takt time, the available time divided by demand, is 5.76 seconds: a part must leave the line every 5.76 seconds to meet demand.
Questions and answers
Is OEE the same as utilisation? No. Utilisation counts time used; OEE adds speed and quality.
Should breaks count as downtime? If the machine is not scheduled during breaks, exclude them from planned time.
How often should I measure? Every shift, ideally automatically.
Using the calculator
Enter planned time, stops, ideal cycle time and counts to get availability, performance, quality, OEE and the parts lost to each, or switch to capacity mode to plan machines for a demand. Everything runs in your browser.