How to Write a Non-Conformance Report and Close It Properly

What a good NCR contains, how to choose a disposition, why root cause and verification come before closure, and how an NCR log shows where problems start.

Saizul Amin
Saizul Amin7 Nov 2026 · 3 min read
How to Write a Non-Conformance Report and Close It Properly

How to Write a Non-Conformance Report and Close It Properly

A non-conformance report, or NCR, records that a product, material or process did not meet a stated requirement, and what was done about it. ISO 9001 asks organisations to identify and control nonconforming outputs (clause 8.7) and to take corrective action to remove the cause (clause 10.2). An NCR is the usual way to show both.

What a good NCR contains

  • A unique number and date, so the report can be traced.
  • Where it was found: incoming inspection, in-process, final inspection, a customer complaint, an internal audit or a supplier.
  • The part or process and quantity affected.
  • A factual description: what was observed, how many, and how it was measured.
  • The requirement not met: a drawing and revision, a specification, a standard clause. Without this, the report is an opinion.
  • Evidence, usually photos.
  • Disposition, cost, root cause, corrective action, owner and due date.
  • Status and sign-off, for the disposition decision and for closure.

Choosing a disposition

The disposition is the decision on the affected items. The common choices are:

  • Use as is: the item is accepted despite the deviation. This often needs customer or design authority approval.
  • Rework: bring the item fully into specification.
  • Repair: make it fit for use, though not to the original specification. This usually needs approval too.
  • Scrap: destroy or recycle it.
  • Return to supplier: send it back for replacement or credit.
  • Regrade: use it for a different application where it does meet the requirements.

Disposition deals with the items in hand. It is not the same as corrective action, which deals with the cause so that the problem does not happen again.

Worked example

The Non-Conformance Report (NCR) Builder includes three NCRs for a components manufacturer.

NCR-2026-031 was raised at incoming inspection. A thread pitch gauge failed on 12 of 50 samples from a batch of 2,000 M8 hex bolts, against drawing 1102 rev C and ISO 4017. The batch was returned to the supplier, at a recorded cost of 380. The root cause was that the supplier mixed batches at packing, and the corrective action was to request an 8D from the supplier and raise the incoming sample size to 80 for the next three batches. The status is action in progress.

NCR-2026-032 came from final inspection: weld spatter on the visible face of 14 brackets, against cosmetic standard CS-02. The brackets were reworked for 210. The spatter guard was worn, so it was replaced and added to the weekly preventive maintenance. The report was closed and verified by J. Smith a day after the action was due.

NCR-2026-033 is a customer complaint: three brackets with a hole position 0.4 mm out against a tolerance of ±0.2 mm. The disposition is still pending and no root cause has been recorded, which is correct for a report raised only days ago.

The log shows three NCRs, two still open and a total cost of 590. Grouping by source shows one each from incoming inspection, final inspection and the customer. Over a year, that view tells you whether problems are being caught in-house or escaping to customers.

Common mistakes

Describing a cause instead of the problem. "Operator error" is not a description. State what was found and what it should have been.

Leaving out the requirement. If you cannot quote the drawing or specification, check whether there really is a non-conformance.

Closing on disposition. Scrapping the parts deals with the items, not the cause. Close the NCR only after the corrective action is in place and verified.

Closing without a root cause. The log warns about this, and auditors look for it.

Using as is without approval. Accepting nonconforming product usually needs the customer or design authority to agree. Record who approved it.

Ignoring cost. Even rough costs per NCR add up, and a cost total is often what gets a recurring problem funded.