How to Read a Microsoft Project XML Plan Without Project
What an MSPDI file contains, how to read predecessors, slack and the critical path, and a worked example of a small office move plan viewed in the browser.

How to Read a Microsoft Project XML Plan Without Project
Project plans travel. A contractor sends a programme, a consultant shares a rollout schedule, a lecturer hands out a sample plan. Often the file was made in Microsoft Project, and the person receiving it does not have a licence. The usual workaround is a PDF printout, which loses the details you most want to check: the links between tasks, the slack and the critical path.
The MSPDI format
Microsoft Project can save any plan as XML through File, Save As. The schema is called MSPDI, the Microsoft Project XML Data Interchange format, and other planning tools, such as ProjectLibre and GanttProject, can export the same thing. One file holds:
- Tasks with an ID, a WBS code, a name, an outline level, start and finish dates, a duration, percent complete, total slack, a critical flag and links to other tasks.
- Resources such as people, materials or cost items, with rates and maximum units.
- Assignments saying which resource works on which task, with units and hours of work.
Durations are stored in hours and slack in tenths of a minute, so the raw XML is hard to read. A viewer converts them back into days using the working day length stored in the file.
Worked example
The Microsoft Project XML viewer comes with a sample plan called office-move.xml. When it is opened, the summary shows the project name Office move, a start of 2026-01-05, a finish of 2026-02-27, 5 tasks, 1 milestone, 5 critical items, 2 resources and 48 percent done.
The Tasks tab has 8 rows:
| ID | WBS | Name | Duration | Predecessors | Slack |
|---|---|---|---|---|---|
| 1 | 1 | Planning (summary) | 10d | 0d | |
| 2 | 1.1 | Agree budget | 5d | 0d | |
| 3 | 1.2 | Choose movers | 5d | 2FS | 0d |
| 4 | 2 | Fit-out (summary) | 25d | 0d | |
| 5 | 2.1 | Network cabling | 15d | 3FS | 0d |
| 6 | 2.2 | Furniture delivery | 5d | 3FS+10d | 10d |
| 7 | 2.3 | Test network | 10d | 5FS | 0d |
| 8 | 3 | Move day (milestone) | 0d | 7FS, 6FS | 0d |
Read the predecessor column like Project does. 2FS means finish-to-start after task 2: Choose movers starts when Agree budget finishes. 3FS+10d on Furniture delivery adds a lag of 10 working days after Choose movers. Move day waits for both Test network and Furniture delivery.
Slack tells you how far a task can slip before it delays the end date. Furniture delivery has 10 days; every other working task has none, and they are flagged critical. In the Gantt tab those critical bars are red, Furniture delivery is blue, and Move day is a purple diamond on 27 February. The darker band inside each bar shows progress: Agree budget and Choose movers are complete and Network cabling is 60 percent done.
The 48 percent figure is weighted by duration. Agree budget and Choose movers, 5 days each, are fully done, Network cabling contributes 60 percent of its 15 days, and the remaining tasks have not started. That gives 19 done days out of 40.
The Resources tab lists a Facilities manager at a standard rate of 45 and an IT contractor at 65 with up to 2 units. The Assignments tab shows the contractor on Network cabling at 2 units for 240 hours and on Test network for 80 hours.
Getting the XML
In Microsoft Project, choose File, Save As, then XML Format. If you only have the .mpp file and no Project, open it in ProjectLibre, which is free, and export it as MS Project XML. Ask the sender for the XML version where possible; it is a normal request in construction and IT work.
Common mistakes
Opening the .mpp directly. The binary format is not read. Convert it to XML first.
Treating the critical flag as recalculated. The viewer shows what Project saved. If the sender changed dates without rescheduling, the flags may be out of date. Nothing is recalculated here.
Confusing summary progress with task progress. The percent on a summary row comes from Project. The summary figure on this page is weighted by duration across working tasks only, so the two can differ.
Missing lag units. A lag shown as +10d is in working days. Lags stored as a percentage or in elapsed time are less common and are best checked in the original program.
Reading slack on summary tasks. Summary rows often show 0d slack because Project does not calculate it in the same way. Look at the working tasks underneath.
Sharing what you find
Export the plan to Excel to add your own comments column, or save the tasks as CSV for a quick import into another tool. Your questions back to the planner will be sharper when you can point to a task ID, a link and its slack.