Keeping a LOLER Register for Lifting Equipment
What LOLER thorough examinations are, the 6 and 12-month intervals for equipment and accessories, and how to keep a register that flags overdue items.

Keeping a LOLER Register for Lifting Equipment
Forklifts, hoists, scissor lifts, slings and shackles all fall under the Lifting Operations and Lifting Equipment Regulations 1998, known as LOLER. Regulation 9 requires lifting equipment to be thoroughly examined by a competent person at set intervals, and the employer has to keep the reports and act on any defects. In practice most sites rely on an insurance engineer or an inspection company, and the risk is not the examination itself but losing track of when each item is due.
The intervals
Unless there is an examination scheme drawn up by a competent person, the usual intervals are:
- every 6 months for lifting accessories, such as slings, chains, shackles and eyebolts, and for any equipment used to lift people, such as a MEWP or passenger lift;
- every 12 months for other lifting equipment, such as a forklift's mast and forks or an overhead hoist.
Equipment also needs examining before first use, after installation at a new location and after anything that could affect its safety, such as damage or a major repair. HSE guidance L113 explains the details.
What a register should show
A good register answers four questions at a glance: what the item is, how much it can lift, when it was last examined and when the next examination is due. It should also show any defect from the last report and whether the item is in use, out of service, repaired or gone.
Worked example
The LOLER Thorough Examination Register opens with four items at Northbank Distribution Centre.
- A 2.5 tonne counterbalance forklift, examined on 12 February 2026, is next due on 12 February 2027 on the 12-month interval.
- An 8 metre scissor lift for two people, examined on 3 April 2026, was due on 3 October 2026 because equipment that lifts people goes on 6 months. It is now flagged OVERDUE: do not use.
- A set of webbing slings, examined on 20 June 2026, is due on 20 December 2026. From 20 November it comes inside the 30-day warning.
- An electric chain hoist, examined on 30 October 2025 with a worn pendant cable noted, was due again on 30 October 2026 and is also overdue.
So of four items, two are overdue and should be taken out of use until examined. The hoist also had a defect that needed fixing within a month; the register shows whether that was done only if someone updates the status.
Running the register day to day
- Add every item, including small accessories. Slings and shackles are the items most often missed.
- Put the report number against each examination so you can find the paper or PDF quickly.
- Copy each defect from the report and change the status when it is repaired.
- Mark scrapped items as Disposed instead of deleting them, so the history remains.
- Check the due list every month and book the engineer in good time.
Common mistakes
- Treating a forklift as one item when it lifts people. If it is fitted with a working platform, the 6-month interval applies.
- Forgetting accessories bought mid-year. New slings need recording, and a certificate of conformity is not the same as a thorough examination.
- Leaving defects open. A report that lists a defect with a timescale is an instruction to act.
- Confusing inspections with examinations. Daily pre-use checks by operators are important but do not replace the thorough examination.
- Keeping the register but not the reports. The reports are the legal record; the register is your index to them.
Next steps
Load the example, then replace it with your own equipment and the dates from the last reports. Set the warning period to suit how far ahead your inspection company needs booking. The register is a record-keeping aid that follows HSE guidance; it is not safety advice and does not replace the competent person's examination.