Lessons Learned That Get Used: How to Run a Lessons Register

How to capture specific lessons with categories and recommendations, find repeat problems across projects and turn lessons into changes in practice.

Saizul Amin
Saizul Amin7 Nov 2026 · 3 min read
Lessons Learned That Get Used: How to Run a Lessons Register

Lessons Learned That Get Used: How to Run a Lessons Register

Almost every project ends with a lessons learned session, and almost every organisation repeats the same mistakes anyway. The problem is rarely the session. It is that lessons are written as vague comments, filed in a closure report nobody reads, and never connected to the next project's plan. A register that is searchable across projects, with a recommendation and a follow-up owner for each lesson, changes that.

Capture lessons during the project

Waiting until closure means people have forgotten the details or moved on. Add lessons at the end of each phase, after a major issue or at a regular retrospective. Record the phase in which the lesson arose, because a planning lesson is most useful to the next project's planning team.

What to write

Each lesson needs a few elements:

  • Type: did it go well or does it need improving? Good practice is as worth repeating as problems are worth avoiding.
  • Category: scope, schedule, cost, quality, resources, communication, risk, procurement, stakeholders or technical. Categories are how you find patterns later.
  • What happened: a specific event, not a feeling. "Key users were booked on other work during testing" can be acted on; "users were not engaged" cannot.
  • Impact: low, medium or high, so readers can focus on what mattered.
  • Recommendation: an instruction another project could follow, written in the imperative.
  • Owner and status: who will turn the recommendation into a change, and whether that has happened.

Worked example

The Lessons Learned Register starts with four lessons from three projects.

On a CRM roll-out, key users were booked on other work during testing. The impact was high, and the recommendation was to agree user test time with line managers at kick-off and put it in the plan. The PMO adopted it. The same project also recorded something that went well: a weekly 15-minute demo kept stakeholders engaged, and short weekly demos were adopted for software projects.

On a warehouse racking project the racking arrived without anchor bolts and two days were lost. The recommendation, to check the packing list against the order on delivery day, is in progress with the site lead.

On an office move, IT staff were not available on move weekend. The recommendation is to book IT support for move dates two months ahead, and it has not started yet.

Look at the register as a whole. Three of the four lessons are to improve, and two of those are in the resources category, on different projects, about people not being available when needed. The register points this out and suggests a standard fix. That is the real payoff: rather than each project manager remembering to book people early, the PMO can add a resource confirmation step to the project start-up checklist.

Using the register at the start of a project

The best time to read lessons is at kick-off. Search for words related to the new project, such as testing, supplier or move, and read the recommendations across every project, not just similar ones. Print the lessons report for a comparable past project and go through it with the new team.

Common mistakes

Blame instead of learning. Write about the process, not the person. People will stop contributing if lessons become a record of who got it wrong.

Only recording problems. Things that went well are easier to repeat than problems are to avoid. Capture them.

Recommendations nobody owns. A recommendation without an owner and a status will not change anything. Review open follow-ups at PMO meetings.

Too many categories or none. A short fixed list makes grouping meaningful. Free-text categories end up with ten spellings of the same thing.

Lessons hidden in documents. A closure report in a project folder is invisible to the next team. Keep lessons in one register that every project can search.

Never closing the loop. Mark a lesson Adopted only when the template, checklist or process has actually changed, and No action when the team decides it is not worth changing.