How to Prepare an Interim Valuation and Application for Payment on a JCT Contract
A step-by-step guide to interim valuations: measured work, variations, materials, retention, previous certificates, VAT, the reverse charge and CIS.

Cash flow on a building job depends on the monthly application for payment. A clear, well-supported application is easier for the quantity surveyor to agree and harder for a payer to cut. A muddled one invites queries, delays and pay less notices. The good news is that the structure is the same on almost every JCT contract, whether it is a Minor Works job on a house or a Design and Build contract for a block of flats.
Start from the contract sum analysis
The basis of every valuation is the breakdown of the contract sum into lines: preliminaries, substructure, frame, roof, envelope, finishes, services and so on. Each month you estimate how much of each line is complete. A line worth £124,000 that is 80% done has earned £99,200. Percentages should be realistic and defensible, ideally supported by site photos, a programme or measured quantities. Preliminaries are often valued in proportion to time on site rather than physical progress.
Add variations separately
Every instruction that changes the work is a variation and should be listed on its own with its instruction number, a description, its value and how far it is complete. Show the status honestly: agreed, instructed but not yet valued, submitted for agreement or disputed. A quantity surveyor is much more likely to include a variation that is clearly identified than one hidden inside a measured line.
Materials on and off site
Materials delivered to site and properly protected are normally included in the valuation even before they are built in. Materials stored elsewhere, such as windows at a factory, are only included if the contract allows it, usually as listed items with proof that ownership has passed, separate marking and insurance, and sometimes a bond. Bricks sitting at a merchant's yard in your name do not qualify. Next month, once they are fixed, their value moves into measured work and the materials figure falls.
Retention and what it applies to
Retention is the slice of the valuation the employer keeps as security for defects, typically 3% under JCT and often 5% in subcontracts. It is usually taken on the value of work, variations and materials, but not on loss and expense or fluctuations. Half is released at practical completion and the balance when defects are made good. After deducting retention and everything already certified, what remains is the net amount due for this month.
VAT, the reverse charge and CIS
Most building work is standard-rated at 20%. New dwellings are zero-rated and some energy-saving work or conversions may be reduced-rated. Where a VAT-registered subcontractor supplies construction services to a VAT-registered contractor who is registered for CIS and is not an end user, the domestic reverse charge applies: the invoice shows no VAT and the customer accounts for it. A subcontractor paid under CIS also has 20%, or 30% if not registered, deducted from the labour element unless it holds gross payment status.
Building the application
The Interim Valuation and Application for Payment Builder (JCT) puts all of this in one place. Enter or import the contract lines with values and percentages, list variations with their status, record materials on site and listed items, and add any previous certificates. The summary shows the gross valuation, retention at the right stage, previous certificates, the net due, VAT or the reverse charge note, any CIS deduction and the amount payable, together with warnings about unagreed variations and unlisted off-site materials. Print the application or save it as a PDF, and when the month closes the next application button carries the figure into the list of previous certificates.
Tips for a smoother month
Submit on the date the contract requires, because the application date can fix the due date. Keep the same line structure every month so the surveyor can compare like with like. Attach evidence for big jumps in percentage complete. Agree variations as you go rather than leaving them for the final account. And diarise the payer's notice deadlines, because if a payment notice does not arrive in time, your application may become the sum that has to be paid.