How to Write an Inspection and Test Plan (ITP) with Hold Points

What an ITP contains, how hold, witness, review and surveillance points work, how to write acceptance criteria and how to agree the plan before work.

Saizul Amin
Saizul Amin7 Nov 2026 · 4 min read
How to Write an Inspection and Test Plan (ITP) with Hold Points

How to Write an Inspection and Test Plan (ITP) with Hold Points

An inspection and test plan, usually called an ITP, lists every inspection and test a piece of work must pass, the acceptance criteria for each, who must be involved and what record will prove it was done. It is agreed before work starts, so nobody discovers on the morning of a concrete pour that the engineer expected to inspect the reinforcement first.

ITPs come from quality management practice. ISO 9001 clause 8.6 requires planned arrangements to verify that requirements are met before products and services are released, and on construction projects the ITP is the usual way to show those arrangements for each work package.

The parts of an ITP

The header names the work package, project, contractor, client or engineer, the specification and drawings, and the revision of the plan. The body is a table of activities. Each row has:

  • the activity, such as reinforcement fixing;
  • acceptance criteria that can be measured, such as cover 40 mm plus or minus 5;
  • the reference clause or standard;
  • the frequency, such as each pour;
  • the involvement of each party;
  • the record that will be kept.

Involvement uses short codes. H is a hold point: work stops until that party inspects and releases it. W is a witness point: the party is notified and may attend, but work can continue if they do not. R is a review of records and S is surveillance or spot checking.

Worked example

The Inspection and Test Plan Builder concrete slab template, ITP-03-001, covers a reinforced concrete ground floor slab with six activities.

Sub-base compaction must achieve a plate bearing value of at least 40 MN/m². The contractor holds and the client witnesses, and the record is a test certificate. The damp-proof membrane must have laps of at least 300 mm, taped with no tears; the contractor holds and the client reviews the checklist.

Reinforcement fixing is the critical point. Bar size, spacing and 40 mm cover are checked against the bar schedule on every pour, and both the contractor and the client have hold points, recorded on a pre-pour sign-off. No concrete is ordered until both have signed.

Concrete deliveries are checked by ticket for C32/40 and slump class S3, cube samples are taken at one set per 50 m³ with a third-party hold for the laboratory, and surface regularity is checked to SR2 with a level survey.

The approval notes set 24 hours' notice by email for hold and witness points. On the printed plan, hold cells are red and witness cells amber, so site staff can see the stopping points at a glance.

An electrical template follows the same pattern with BS 7671 tests, including insulation resistance of at least 1 MΩ at 500 V DC and RCD trip times.

Agreeing the plan

Send the draft ITP to the client or engineer with the method statement and get it approved before the work starts. Agree the notice period for hold and witness points and who receives the notice. Then use the plan on site: the signed and date column becomes the running record of each inspection.

Common mistakes

Criteria that cannot fail. "Good workmanship" is not an acceptance criterion. Write a number, a tolerance or a named standard. The builder's checks warn when an activity has none.

Too many hold points. If every activity is a hold for the client, work stops constantly and inspectors stop turning up. Keep holds for points that cannot be checked later, such as reinforcement before concrete covers it.

No hold or witness on critical work. The opposite problem. The checks flag activities where nobody has an H or W so you can confirm that review alone is enough.

Copying a template blindly. Template values are examples. Replace them with the figures in your own specification.

Forgetting the record. Every row should name the evidence: a certificate, a checklist, a survey. Without it, an inspection that happened cannot be proved.

Final word

The plan prints from the live preview and downloads as Word or a web page, with saved versions in your browser. It is a planning document, and the responsible engineer must review and approve its content.