Fleet Availability: FMC, PMC, NMCM and NMCS Explained

Fleet Availability: FMC, PMC, NMCM and NMCS Explained

Every morning, someone in maintenance control has to answer one question for operations: what can fly today? A good status board answers it at a glance, and over time it also shows why aircraft are on the ground. The categories used by many military and some civil operators make that second question easy to read.

The categories

  • FMC, fully mission capable: the aircraft can do every task it is equipped for.
  • PMC, partially mission capable: it can fly but with a restriction, such as day only, no icing conditions or one radio inoperative.
  • NMCM, not mission capable, maintenance: grounded because work is being done or needs doing.
  • NMCS, not mission capable, supply: grounded because a part has not arrived.
  • Depot or deep maintenance: away for major inspection or overhaul.

The split between NMCM and NMCS is the useful part. A fleet with many NMCM aircraft is short of hands, hangar space or time. A fleet with many NMCS aircraft has a spares problem, and no amount of overtime will fix it.

Availability rate

The simplest measure is:

Availability rate = (FMC + PMC aircraft) / total aircraft x 100

Some organisations count only FMC, some exclude depot aircraft from the total, and many measure over hours in a reporting period rather than a single snapshot. Whatever rule you use, write it down and keep it consistent so the trend means something.

Worked example

A small training unit has four aircraft on Tuesday morning:

  • ZZ121, trainer: FMC, 3,402.5 hours, next 150-hour phase at 3,450. 47.5 hours to go.
  • ZZ122, trainer: NMCS, waiting for a fuel pump, ETIC 05 Nov 12:00. 20 hours to the next primary inspection.
  • ZZ123, trainer: PMC, night flying not permitted because a landing light is out. 4,111 hours, 50-hour inspection due at 4,118: only 7 hours left.
  • ZZ201, utility helicopter: NMCM, ETIC 04 Nov 17:00.

Available aircraft: ZZ121 and ZZ123, so the rate is 2 / 4 = 50%. One aircraft is grounded for supply and one for maintenance.

The board also tells the planner something operations may not notice: ZZ123 is available but will hit its 50-hour inspection after about 7 more flying hours. If it is programmed for a full day of sorties, it will be grounded by the afternoon. With a 10-hour warning band, it should already be flagged.

Running the board well

  • Update status the moment it changes, and date every line.
  • Give every grounded aircraft an ETIC and revise it as soon as it slips.
  • Write restrictions for PMC aircraft in plain words, because crews will plan from them.
  • Review NMCS items daily with stores, and escalate long-lead parts early.
  • Keep the hours-to-inspection column visible so operations can plan around it.

Showing the board

A status board earns its keep when operations can read it without asking questions. Colour coding helps: green for fully capable, yellow for partially capable, red for anything grounded. Keep it on a screen where planners and crews pass, add the date and time it was last updated, and print a copy for the morning meeting so decisions are taken from the same picture.

Common mistakes

  • Counting a PMC aircraft as fully available without passing on its restriction.
  • Leaving an old ETIC on the board after the date has passed.
  • Lumping supply and maintenance groundings together, which hides the real cause.
  • Calculating the rate differently from one week to the next.
  • Forgetting that an aircraft near an inspection is about to become unavailable.

This article explains common reporting terms for training and is not operational advice. Your organisation's reporting rules and the aircraft's technical records decide each aircraft's status.

Using the Fleet Status Board and Availability Dashboard

On shobfree.com you can enter each aircraft's tail, type, status, current hours and next inspection, with an ETIC for grounded aircraft and remarks for restrictions. Counters show fleet size, aircraft available, the availability rate, NMCS aircraft and inspections inside your warning band, a board groups aircraft by status, and a summary breaks the rate down by type. Download the colour-coded HTML board for a briefing screen. The example loads the four aircraft above.

Completely freeNo cost, no sign-up
Files stay privateEverything runs in your browser
Easy in your languageAvailable in many languages