Drawing Register Basics: Keeping Revisions Current on Site
How a drawing register tracks revisions and status, decides which issue is current, flags superseded drawings and helps stop work from old revisions.

Drawing Register Basics: Keeping Revisions Current on Site
Building from a superseded drawing is one of the most expensive mistakes on a construction site. A wall set out from revision A when revision B moved it 300 mm has to come down, and the argument about who pays can last longer than the rebuild. A drawing register is the simple control that prevents it: a list of every document issued on the project, with its revision, status and date, so anyone can check which version is current.
Issues, not drawings
The most reliable registers record issues rather than drawings. Each time a drawing is issued, a new line goes in with the number, title, revision, status, date and a note of what changed. Nothing is overwritten. The history of each drawing is then visible in order, and the current revision is simply the most recent issue.
Status matters as much as revision. A drawing issued For information or as Preliminary should not be built from, even if it is the latest. Typical statuses are Preliminary, For information, For approval, For construction and As built. Projects working to ISO 19650 use suitability codes for the same purpose.
Worked example
The Drawing and Document Register sample has five issues of three drawings.
Ground floor plan A-101 appears three times: P1 Preliminary on 4 August, revision A For construction on 15 September and revision B For construction on 30 October, with the note "Kitchen opening widened (RFI-001)". The register ticks revision B as current and marks P1 and A as superseded. Structural drawing S-201 rev B and mechanical drawing M-401 rev P2 each have one issue, so both are current.
The stat cards read 3 documents, 5 issues logged, 2 current drawings For construction and 2 superseded issues. The insights panel adds a warning: M-401 is current but still Preliminary, so the ductwork contractor should not fabricate from it yet.
Open the revision history for A-101 and you get a printable sheet showing all three revisions with dates, statuses and descriptions. That sheet answers the question "when did the kitchen opening change?" in seconds.
How the current revision is chosen
The register treats the issue with the latest date as current. A tie on the same day goes to the higher revision code. This mirrors site practice, where the newest transmittal replaces the copy on the wall. It also means dates need care: a mistyped year can make an old revision look current.
Using the register day to day
Update the register at the moment a drawing is issued or received, not at the end of the week. Link each revision to its cause, such as an RFI number or a client comment, in the description. Before a package of drawings goes out, check the revisions against the register, and list them on a transmittal so you can prove what was sent.
On site, the register is only half the job. Old prints need to be removed or stamped superseded, and the drawing rack or tablet folder checked against the register regularly.
Common mistakes
Editing the revision in place. Changing A to B on one line loses the history and the proof of what was issued when. Add a new line for every issue.
Ignoring status. A current drawing marked Preliminary is not a construction drawing. Watch the status column, not just the tick.
Mixed numbering. If the architect writes A-101 and the contractor types A101, the register treats them as two documents. Agree one format and stick to it.
No discipline field. Without it, a register of 400 drawings is hard to filter for a design team meeting. The By discipline summary counts current documents for each discipline.
Keeping the only copy in a browser. The register is stored on the device you use. Export a CSV for Excel and a JSON backup, and keep them in the project folder.
What it does not do
The register records what you enter. It does not read title blocks, enforce ISO 19650 naming or store the drawing files. A tick shows the latest issue, not that the drawing has been approved, so your document controller still needs to check status and approvals.