How to Write and Track Construction RFIs That Get Answered
How to word a construction RFI, add a proposed solution, set response dates, track cost and time impact and keep a numbered log that stands up later.

How to Write and Track Construction RFIs That Get Answered
Every construction project produces questions that the drawings do not answer. A lintel schedule disagrees with a plan, a finishes schedule names a different floor from the specification, or a detail is simply missing. The request for information, or RFI, is the formal way to put that question to the designer and get a written answer before the work goes ahead.
An RFI matters for two reasons. On site, it stops people guessing. Commercially, it is evidence: a dated question and a dated answer show when information was needed and when it arrived, which is often the starting point for a variation or an extension of time.
What a good RFI contains
A useful RFI is short and specific. It needs a unique number, a subject line that someone can search for later, the person or firm it is addressed to, and the exact drawing or specification reference. The question should describe the conflict or the missing information in one or two sentences. Where you can, add a proposed solution. A designer can confirm "use a 2.7 m steel lintel to the manufacturer's tables" in a minute, while an open question may sit in an inbox for a week.
Each RFI also needs a date sent and a date by which an answer is needed. If your contract sets a period for the design team to respond, use it. If not, agree one at the start of the project and apply it consistently.
Worked example
The Construction RFI Log and Form opens with three RFIs on a sample housing block. The default response time in the settings is 7 days.
RFI-001 asks the structural engineer to confirm a lintel over a widened kitchen opening, referencing S-201 rev B, and proposes a 2.7 m steel lintel. It was sent on 20 October with no specific date requested, so the log sets the due date to 27 October. The answer, "use 2.7 m lintel type L-3 as proposed", came back on 24 October, a turnaround of 4 days. The cost impact is marked Possible because the longer lintel costs more.
RFI-002 asks the architect for the fire stopping product at a services riser. A response date of 4 November was agreed, and no answer has arrived, so from 5 November the log flags it as overdue.
RFI-003 points out that the finishes schedule says porcelain tile in the lobby while the specification says vinyl. Its cost impact is marked Yes, so the insights panel reminds the team to consider giving notice under the contract.
The summary shows 3 RFIs, 2 open, 1 overdue and an average response of 4.0 days. That average becomes a useful figure at progress meetings when you want to show that late answers are holding up work.
Keeping the log useful
Number RFIs in a single sequence and never reuse a number, even if an RFI is withdrawn. Record the answer in the log in the designer's words, not your summary of it. When an answer leads to a revised drawing, note the new revision in the drawing register and close the RFI only when the revised information is on site.
The due list can be exported as a calendar file, so the people chasing answers see the dates in Outlook or Google Calendar alongside their other work.
Common mistakes
Asking several questions in one RFI. If one part is answered and another is not, the RFI can never be closed cleanly. Raise one question per RFI.
Using RFIs to request changes. An RFI asks for information. If you want to propose a different product to save money, that is a change or substitution request and should follow the contract procedure for it.
Vague references. "See drawings" forces the designer to search. Name the drawing number and revision, and attach a marked-up sketch or photo.
Ignoring impacts until the end. Flag cost and time impact when the RFI is raised, not months later. Contracts often require notice within a set period.
Leaving the log in one person's head. Export the log regularly, because data in a browser stays on that device. A CSV file opens in Excel for the commercial team, and the JSON backup keeps photos too.
Before you rely on it
The response period in the tool is a setting, not a contract term, and marking an impact in the log is not the same as notifying the client. Check your contract for the procedure and time limits, and have notices issued in the form it requires.