Certified Payroll for Davis-Bacon Projects: How to Prepare WH-347
What certified payroll is, how prevailing wage and fringe benefits work, overtime rules, the statement of compliance and the mistakes that trigger audits.

Certified Payroll for Davis-Bacon Projects: How to Prepare WH-347
Winning a federally funded construction job brings a weekly chore: certified payroll. Every contractor and subcontractor on a Davis-Bacon covered project must show, week by week, that workers were paid at least the prevailing wage for their classification. Errors can delay payments, trigger audits and lead to back wages. This guide explains the process and how the free certified payroll WH-347 builder helps.
Start with the wage determination
The contract includes a wage determination listing each classification of work, such as laborer, cement mason or operator, with a base hourly rate and a fringe benefit rate. Copy these into the builder's wage determination tab. If workers will do work not listed, ask the contracting officer for an additional classification before they start.
Record hours by classification and day
Certified payroll shows hours for each day of the week. If a worker performs work in two classifications, record the hours separately and pay each at its own rate. The builder takes hours for Sunday through Saturday, totals them, and splits straight time and overtime.
Overtime
The Contract Work Hours and Safety Standards Act requires overtime at one and a half times the basic hourly rate for hours over 40 in the workweek. The fringe benefit rate is not multiplied: it is paid for every hour worked, straight or overtime, but without the premium.
Fringe benefits
Fringe benefits can be met by contributions to bona fide plans such as health insurance, pensions and vacation funds, by paying the amount in cash with wages, or by a combination. Cash fringe is taxable wages; plan contributions generally are not. In the builder, tick "fringe paid in cash" for workers who receive it as wages, and the amount is added to gross pay.
The builder compares each worker's rate plus fringe with the determination for their classification and flags any shortfall. In the example, a laborer working 42 hours at $31.20 earns $1,341.60 including overtime, while an operator paid $41.00 against a $42.50 determination is flagged as $1.50 an hour short.
Deductions
Only permissible deductions may be made: taxes, deductions required by law, and voluntary deductions authorized in writing that do not benefit the employer. Enter Social Security and Medicare, income tax and other deductions from your payroll system to show net pay.
The statement of compliance
Each payroll needs a signed statement certifying that workers received the full weekly wages earned, no rebates were taken, only permissible deductions were made, rates meet the wage determination, classifications match the work performed, and how fringe benefits were provided. The builder fills in the contractor, project and week and prints the statement with the payroll for signature. Willful falsification is a federal crime.
Weekly routine
Submit a payroll for every week work is performed, numbered in sequence, through the prime contractor to the contracting agency. Mark the final payroll. Keep records for three years after the project is completed. Many agencies now use online systems; the builder's table and CSV export make data entry easier.
Common mistakes
The most frequent problems are misclassified workers, overtime calculated on the wrong rate, fringe benefits that do not add up, missing apprentice registration, and missing weeks. A weekly check against the wage determination prevents most of them.
Limits
The builder prepares information in the WH-347 layout; it is not the official form and not legal advice. State prevailing wage laws, apprentice ratios and agency systems add their own rules. Check your contract and the contracting agency's requirements.