How to Calculate Cable Tray Fill and Choose the Right Tray Width

Add up cable cross-sections, check fill, single-layer width and load against your code's limits, and pick the smallest tray width that leaves spare.

Saizul Amin
Saizul Amin19 Nov 2026 · 4 min read
How to Calculate Cable Tray Fill and Choose the Right Tray Width

How to Calculate Cable Tray Fill and Choose the Right Tray Width

Every electrical project has a moment when someone asks whether another cable still fits in the tray. Guessing is risky: an overfilled tray traps heat, makes cables hard to pull and inspect, and leaves nothing for the next change. The answer is a short calculation that is tedious by hand once a tray carries dozens of cables. The free Cable Tray Fill and Sizing Calculator does it for a whole cable schedule and every tray on the job.

Three checks, one schedule

Most codes and specifications control trays in three ways.

  • Area fill. The total cross-section of the cables must not exceed a share of the tray's usable cross-section.
  • Single layer. Large power cables may have to lie side by side in one layer, so the sum of their diameters must fit the width.
  • Load. The tray and its supports have a rating in kilograms per metre for a given span, published by the maker.

The calculator does all three, but it does not decide the limits. They come from the code adopted where you work, for example NEC 392.22 in the United States, from your client's specification and from the tray catalogue. You type them in; until you do, each tray reads incomplete rather than pass.

Step 1: describe the trays

Add each tray with its name, inside width, usable loading depth and type. The usable depth is what the cables may occupy, usually less than the side rail height. Enter the fill limit, the spare capacity you want to keep for future cables and the maker's load rating for your support span. Spare capacity reduces the limit: a 40 percent limit with 20 percent spare leaves an effective 32 percent for today's cables.

Step 2: build the cable schedule

List each cable type with a tag, a description, its outside diameter and weight per metre from the cable maker's data sheet, the quantity and the tray it runs in. Mark large power cables that must lie in a single layer. If you already have a schedule in a spreadsheet, paste lines of tag, description, diameter, quantity and weight, and they are added to the selected tray.

Step 3: read the results

For each tray the calculator shows:

  • the total cable cross-section, π d² / 4 for every cable,
  • the fill as a percentage of width times usable depth,
  • the width taken by single-layer cables side by side,
  • the load per metre, including any extra load you add for fittings or future cables,
  • the width needed at your limit and the smallest width from your list that meets it.

A cross-section sketch packs the cables in rows, largest first, and marks any that would sit above the usable depth. It is a picture of one possible arrangement, useful for spotting a cable that is simply too large for the tray.

A worked example

A 300 mm ladder tray with 75 mm usable depth carries six 4-core 25 mm² armoured cables of 28.5 mm, two 4-core 95 mm² cables of 41 mm and twelve 3-core 2.5 mm² cables of 13.5 mm. Their cross-sections total about 8 186 mm², a fill of 36.4 percent, and they weigh 29.2 kg/m. The project specification limits fill to 40 percent and asks for 20 percent spare, so the effective limit is 32 percent and the tray is over it. The calculator reports that about 341 mm of width is needed and picks the 400 mm tray from the list. With the maker's rating of 80 kg/m for a 2 m span entered, the load is comfortably within it.

Choosing widths

The list of available widths is editable. Quick buttons fill a common metric series and the 6 to 36 inch series converted to millimetres; replace them with your supplier's sizes. When nothing in the list is wide enough, split the cables over two trays or choose a deeper one.

What else to check

Fill is only one design check. Cable ratings must be derated for grouping in the tray, power, control and data circuits may need segregation or barriers, and bend radius, support spans, fire stopping and tray earthing follow your code and the maker's instructions. NEC users should also note the special rules for single conductors and for large cables in Article 392. Print the tray and cable schedules or export them as CSV for the drawing set, and have the design checked by a qualified engineer.

Completely freeNo cost, no sign-up