How to Write a Business Requirements Document (BRD)
What goes into a BRD, how to describe the as-is and to-be process, how to write testable requirements, and a worked HR example with common mistakes.
&c=%230e7490&k=business)
How to Write a Business Requirements Document (BRD)
A business requirements document records what a business needs from a change and why, before anyone chooses or designs a system. It is the business analyst's main deliverable at the start of a project, and it gives everyone, from the sponsor to the supplier, a shared statement of what success means. A good BRD is readable by managers and precise enough for testers.
What a BRD contains
Most BRDs follow a similar pattern. An executive summary says in a few sentences what is changing. Business objectives say what the change must achieve. A stakeholder list shows who is affected and who decides. A description of the current process, often called as is, and the future process, to be, shows what will be different. Functional requirements list what the solution must do; non-functional requirements list the qualities it must have. Assumptions, constraints and a sign-off table close the document.
Worked example
The BRD builder includes a sample for online leave requests, written as version 0.3 by business analyst K. Owusu. The summary is a single sentence: replace paper leave forms with an online request and approval process linked to payroll.
Three business objectives set the targets: leave approved within two working days, no manual re-keying into payroll, and a live view of each person's balance.
The stakeholders are HR as the process owner, line managers as approvers, payroll as the receiver of approved leave and all staff as requesters.
The process section puts the two versions side by side:
| As is | To be |
|---|---|
| Employee fills in a paper form | Employee requests leave online and sees the balance |
| Manager signs and sends to HR | Manager approves on phone or computer |
| HR updates a spreadsheet and keys into payroll | Approved leave flows to payroll automatically |
Comparing the rows shows where the value lies: the HR step disappears entirely.
The functional requirements are numbered FR-1 to FR-4. Requesting annual, sick and unpaid leave, manager approval and balance updates are Must; a team calendar view is Should. Non-functional requirements cover mobile browsers, storage of personal data in the UK or EU and 99.5% availability in working hours.
The tool shows a warning on this sample: some requirements combine several needs. The cause is FR-2, managers get an email and can approve or reject with a reason. That one line holds two needs, a notification and a decision. Splitting it gives FR-2a, managers receive an email when a request is submitted, and FR-2b, managers can approve or reject a request and must give a reason when rejecting. Each can now be tested on its own.
Writing testable requirements
A tester should be able to read a requirement and say pass or fail. That means one need per line, specific words and a measure where quality is involved. Fast becomes within 2 seconds. Available becomes 99.5% between 08:00 and 18:00 on working days. Each requirement also needs a unique ID so it can be traced to designs and tests later.
Common mistakes
Describing a solution, not a need. Use system X is a solution. Approved leave reaches payroll without re-keying is a need that several systems could meet.
Leaving out the as-is process. Without it, readers cannot see what changes or which steps the new process removes. It also helps spot requirements nobody mentioned.
Forgetting non-functional requirements. Data location, accessibility and availability are often discovered late and are expensive to add then.
Missing stakeholders. Payroll is easy to forget in a leave project, yet it is the team that suffers most if the data arrives in the wrong format.
Signing off too early. A version 0.3 is a draft. Circulate it, resolve comments and save a version at each stage before asking for signatures.
Approval
The sample's sign-off table has the business owner, HR, IT and the business analyst. Agree who must approve at the start, so the final version does not stall waiting for someone who was never consulted.