Pricing Building Variations: Margin, GST and a Clean Variation Register
How builders price variations with margin and GST, why variations must be in writing, and how to keep a register that owners can follow.

Pricing Building Variations: Margin, GST and a Clean Variation Register
On most building jobs the contract price is only the start. Owners change their minds, ground conditions surprise everyone, and authorities ask for extra work. Each change is a variation, and badly managed variations cause more disputes than almost anything else. The Builder's Margin and Variation Pricing Calculator prices each one and keeps the register tidy.
What counts as a variation
A variation is any change to the scope of work in the contract: adding something, removing something, or changing a specification. Examples include upgrading tiles, adding power points, deleting a shed, or excavating rock that was not expected. Some contracts treat provisional sums and prime cost items separately; adjustments to those follow their own clauses.
The legal side
Home building laws in each state require variations on domestic work to be in writing and agreed by the owner before the work is done, with exceptions for urgent work or authority requirements. Some states limit what a builder can recover if a variation was not signed. Commercial contracts usually have their own variation clauses. Either way, writing it down protects both sides.
Pricing a variation
The usual approach:
- Work out the direct cost: labour, materials, plant and subcontractors.
- Add a margin to cover overheads, supervision, insurance, risk and profit. Many builders use 15 to 25%; your contract may set it.
- Add GST at 10% if you are registered.
For a deleted item, the credit is usually the cost without a margin, although some contracts give a credit including margin.
Using the calculator
Enter the original contract sum, the margin and whether the contract sum includes GST. Then list variations, one per line: number, description, cost, and whether the owner has approved it. The register shows each variation's price, GST and total, the approved total, the pending total, the new contract sum, the percentage change and the margin earned.
A worked example
On a A$385,000 contract including GST with a 20% margin:
- V1, stone benchtop upgrade, cost A$4,200: price A$5,040 plus GST, A$5,544 in total.
- V2, six extra power points, cost A$780: A$1,029.60 including GST.
- V4, delete garden shed: a credit of A$2,640 including GST.
- V3, rock excavation, cost A$6,500: A$8,580 including GST, still pending.
The approved variations add A$3,934, a 1.0% increase, and the margin earned is A$996.
Good practice
- Price and get approval before starting. If urgent, confirm by email the same day and follow with a signed form.
- Include any change to the completion date in the variation.
- Attach drawings, quotes or photos.
- Number variations in order and never reuse numbers.
- Add approved variations to the next progress claim, not before.
For owners
Ask for the cost breakdown and margin. If the variation comes from an error in the plans, ask who is responsible. If you are unsure, ask your state's fair trading or building authority for guidance before you sign.
Progress claims
Show approved variations as separate lines in each progress claim, with the variation numbers. Owners and lenders can then reconcile the payments with the register, which avoids delays in construction loan drawdowns.
Latent conditions
Rock, contaminated soil and hidden services are called latent conditions. Many contracts let the builder claim for them as a variation, but only if the owner is told promptly and the condition could not reasonably have been foreseen. Record when the condition was found, take photos and notify the owner in writing before continuing.
Limits
This is an estimating and record-keeping aid, not legal advice. Your contract and your state's building laws govern variations, and nothing you type leaves this page.