Risk Register and Heat Map
List risks with cause, effect, owner and a 5 by 5 likelihood and impact score, track mitigations, compare inherent and residual heat maps and plan reviews.
Tarayıcınızda çalışır. Dosyalarınız cihazınızdan asla çıkmaz. Nasıl kontrol edeceğinizi görün
…
Nasıl yapılır
- 1Name the register
Type the project or business name at the top and set your categories under Reviews.
- 2Add risks
Press + Risk and write the title, cause, effect, category, owner and strategy.
- 3Score them
Choose inherent likelihood and impact, then the residual values you expect after mitigation.
- 4Plan mitigations
Add mitigation actions with owner and due date and tick them when done.
- 5Read the heat map
Open Heat map, switch between inherent and residual and tap a cell to see its risks.
- 6Keep it current
In Reviews press Mark reviewed after each review, then export XLSX, CSV or Print.
Bu araç hakkında
A risk register is only useful if it is kept up to date and if it shows clearly which risks need attention now. This tool keeps the register and the picture together. Each risk has a reference, a title, cause and effect, a category, an owner and a response strategy: reduce, avoid, transfer or accept. Likelihood and impact are scored from 1 to 5 with plain descriptions, once before mitigation (inherent) and once for the level you expect after mitigation (residual). The 5 by 5 heat map shows every open risk by its reference number in a coloured cell, and a click on a cell filters the register. Mitigation actions have owners, due dates and done boxes, review dates warn when they are due or overdue, and the whole register exports to Excel, CSV or a printed report.
Who this is for
Project managers, PMO staff, small business owners preparing for a bank or insurer, event organisers, IT and security leads, and students learning risk management. The register is private to the browser and needs no account.
Scoring and bands
Likelihood runs from 1 Rare to 5 Almost certain; impact from 1 Insignificant to 5 Severe. The score is likelihood × impact, from 1 to 25. Bands are Low (1 to 4), Medium (5 to 9), High (10 to 16) and Critical (20 to 25), each with its own colour. The register is sorted by residual score, then inherent score, so the risks that remain serious after mitigation come first.
Inherent and residual
Inherent is the risk as it stands without new controls. Residual is the level you expect once the mitigation actions work. A risk whose residual score is higher than its inherent score gets a warning, because that usually means the fields are swapped. The status bar shows total exposure (the sum of scores of open risks) before and after mitigation and the percentage reduction.
Heat map
Inherent and Residual buttons switch the matrix. Rows are likelihood from 5 at the top to 1, columns are impact from 1 to 5. Each cell shows the reference numbers of the open risks in it and fades when empty. Tapping a cell lists exactly those risks in the register; tap again or press the cell chip to clear the filter. Closed risks are left out of the map.
Mitigations, owners and reviews
Each risk carries its own list of mitigation actions with owner, due date and done box; the register shows how many are complete. Every open risk has a next review date. The Reviews tab lists reviews that are overdue, due within seven days or missing; Mark reviewed moves the date forward by the default cycle (30 days unless you change it).
Worked example
"Key developer leaves mid-project" is likely enough to score 3 and would cause a major delay, impact 4, so its inherent score is 12 (High). Pair programming and handover notes lower the expected residual to 2 × 3 = 6 (Medium). Across five open risks, exposure falls from 50 to 29, a reduction of 42 %, and one risk whose review date passed three days ago appears in red.
Limits
The 5 by 5 matrix is a simple ordinal tool: a score of 12 is not exactly twice as bad as 6, and the bands are a convention you can question. It is not a quantitative model such as Monte Carlo simulation. The register is kept in one browser; share the XLSX or JSON file with the team.
Çözümlü örnek
Inherent 3 × 4 = 12 (High); after mitigation 2 × 3 = 6 (Medium); total exposure 50 → 29, 42 % lower.
Kısaca
- Kategori: İş ve çalışma
- Tarayıcınızda çalışır, kayıt yok, yükleme yok.
- Girdiğiniz bilgiler cihazınızda kalır.
- İngilizce olarak mevcut.
- İçeriğin son gözden geçirilmesi:
- Resmî kaynak: ISO 31000:2018 Risk management guidelines and the 5×5 likelihood-impact matrix used in project practice
Sık sorulan sorular
How is the risk score calculated?
Likelihood (1 to 5) times impact (1 to 5). Scores from 1 to 4 are Low, 5 to 9 Medium, 10 to 16 High and 20 to 25 Critical.
What is the difference between inherent and residual risk?
Inherent risk is the level without new controls. Residual risk is the level you expect after your mitigation actions are in place.
What do the four strategies mean?
Reduce lowers likelihood or impact, Avoid changes the plan so the risk cannot happen, Transfer moves it to someone else such as an insurer, and Accept means you live with it.
Can I change the band limits?
The bands are fixed at common values. If your organisation uses others, use the score column in the XLSX export.
How do review reminders work?
The Reviews tab and status bar show risks whose review date is overdue or within seven days. There are no emails or pop-ups.
Is my register uploaded?
No. It is stored in this browser. Export XLSX or Save file to share it or keep a backup.
