RAJUK Building Permit Application Checklist

A tracker for each approval stage with dates, file numbers and fees, plus a bilingual checklist of ownership papers, drawings, structural design and NOCs.

브라우저에서 실행됩니다. 파일은 기기 밖으로 나가지 않습니다. 확인하는 방법 보기

…

사용 방법

  1. 1
    Describe the project

    Enter the owner, plot, size, use, floors and the architect and engineer.

  2. 2
    Set up the stages

    Skip the special project permit if it does not apply and set planning days.

  3. 3
    Record each step

    Enter applied and approved dates, the file number, the fee and the status.

  4. 4
    Watch the dates

    See the expected date of each stage and which ones are late.

  5. 5
    Tick the documents

    Mark each paper and drawing ready, with references and notes.

  6. 6
    Print the status

    Print the file status sheet in Bangla or English and save the project.

이 도구 소개

Building a house or an apartment block in the RAJUK area takes more than one approval. First comes the land use clearance, which confirms what the plot may be used for and sets the FAR. Large or special buildings then need a special project permit. Next is the building construction permit on the architectural and structural drawings, and after the building is finished the occupancy certificate confirms it was built as approved. Each stage needs its own set of papers, signatures from registered professionals and fees, and files often stall for weeks because one document was missing or a query was not answered. This tool keeps the whole file in view. The stages tab lists each approval with its status (not started, applied, query raised, approved), the date applied and approved, the RAJUK file number, the fee paid and the number of days you plan for it; the expected date of each stage follows from the one before, and a stage past its expected date without approval is marked late. The documents tab is a bilingual checklist in four groups: land use clearance papers, construction permit papers, drawings and the occupancy certificate.

What the documents list covers

For the land use clearance: the application with the owner's photo and NID, the land deed, latest khatian, mutation and khajna receipt, the mouza map with the plot marked and a site plan with the access road. For the construction permit: the clearance letter, ownership papers or the registered joint venture agreement and power of attorney, the soil test, the structural design signed by a registered engineer, supervision undertakings, NOCs from fire service, civil aviation (for height) or the environment department where needed, and the fee receipt. Drawings include the site plan, every floor plan, elevations and sections signed by a registered architect, the FAR and coverage sheet, setbacks, parking and services. Critical items are marked.

Fees and days

Fees and planning days start blank or as example figures, because the schedule depends on the building and changes with RAJUK's rules. Type the fee from each payment slip; the total is shown.

Limits

This is a tracker for your own file, not a RAJUK service. It does not submit anything, check a file's status online or know the current fee schedule. RAJUK's online permit system and its current document list decide what you must submit.

풀이 예시

A family files for a Ground plus 6 house on a 5 katha plot in Uttara. The land use clearance is applied on 5 January 2026 and approved on 20 February, 46 days. The construction permit is applied on 1 March with 45 planning days, so its expected date is 15 April 2026. The special project stage is skipped. In the documents tab 14 of 18 items are ready; the soil test and the structural design are still open, and the printed status sheet lists both as critical.

한눈에 보기

자주 묻는 질문

What are the stages of RAJUK building approval?

Typically a land use clearance, a special project permit for large or special buildings, the building construction permit and, after completion, the occupancy certificate. Smaller buildings skip the special project stage.

Who must sign the drawings?

Architectural drawings are signed by a registered architect and the structural design by a registered structural engineer. Supervision undertakings are also needed.

What is the land use clearance for?

It confirms the permitted use of the plot under the area plan and states figures such as the FAR. The construction permit drawings must follow it.

Why are the fees blank?

Fees depend on the floor area and use and change over time. Enter what you pay from the slips; the tool adds them up rather than guessing a schedule.

Can I add my own documents?

Yes. Add items to any section, mark them critical, edit the English or Bangla text and export the list to Excel.

Does this submit my application?

No. Apply through RAJUK's online system. This tool only helps you prepare and track the file.

완전 무료요금 없음, 가입 없음
파일은 비공개로 유지됩니다모든 작업이 브라우저 안에서 이루어집니다
내 언어로 쉽게여러 언어로 제공