OEE and Production Capacity Calculator
Enter planned time, downtime, ideal cycle time and total and good counts to get availability, performance, quality and OEE with the parts lost to each, or work out how many machines a demand needs.
يعمل في متصفحك. ملفاتك لا تغادر جهازك أبدًا. شاهد كيف تتحقق
…
كيف تفعل ذلك
- 1Choose OEE or capacity
Measure or plan.
- 2Enter times
Planned time and stops.
- 3Enter the ideal cycle
Seconds per part.
- 4Add counts
Total and good parts.
- 5Read OEE and losses
In percent and parts.
عن هذه الأداة
Overall equipment effectiveness (OEE) measures how much of a machine's planned time produces good parts at full speed. It multiplies three factors: availability (run time over planned time, losing breakdowns and changeovers), performance (actual output against the ideal rate, losing small stops and slow cycles) and quality (good parts over total parts, losing scrap and rework). This calculator computes all three and the OEE, and converts each loss into lost parts so you can see where the biggest gains lie. A capacity mode works out how many machines and hours a weekly demand needs at a given OEE, with the takt time.
Who this is for
Production managers, lean and TPM coordinators, industrial engineers, plant controllers and maintenance leaders.
The three factors
- **Availability** = run time / planned production time. Run time = planned time − stops. - **Performance** = (ideal cycle time × total count) / run time. - **Quality** = good count / total count. - **OEE** = A × P × Q, also equal to (good count × ideal cycle time) / planned time.
Benchmarks
- 85 %: world class for discrete manufacturing (90 % availability, 95 % performance, 99.9 % quality). - 60 %: typical. - 40 %: common when OEE is first measured. Benchmarks differ widely by industry; trends at your own plant matter more.
The six big losses
1. Breakdowns, 2. setup and adjustments (availability); 3. small stops, 4. reduced speed (performance); 5. start-up rejects, 6. production rejects (quality).
Worked example
A 420-minute shift with 47 minutes of stops leaves 373 minutes of run time. With an ideal cycle time of 1.0 s, 19,271 parts made and 18,848 good: availability 88.8 %, performance 86.1 %, quality 97.8 % and OEE 74.8 %. The shift could have made 25,200 parts; 2,820 were lost to stops, 3,109 to speed losses and 423 to rejects.
Capacity planning
Machine hours needed = demand × ideal cycle time / OEE. For 50,000 parts a week at 1 s per part and 75 % OEE, you need 18.5 hours a week, well within one machine on two 8-hour shifts. The takt time, available time divided by demand, is 5.76 s.
Common pitfalls
- Using a slow "standard" cycle time instead of the ideal one inflates performance. - Excluding planned stops that are really losses hides improvement potential. - Performance above 100 % means the ideal cycle time is wrong.
Example uses
A packaging plant compares the OEE of three lines and finds that small stops, not breakdowns, cost the most. A planner checks whether one machine can handle a new order or a second shift is needed. A maintenance team tracks availability before and after a TPM programme.
Improving OEE
Start with the biggest loss: reduce changeover time with SMED, fix recurring small stops, and remove causes of start-up scrap. Measure every shift so that improvements show quickly.
Limits
OEE suits discrete production; continuous processes may use other metrics. This is not professional advice.
مثال محلول
420 min planned, 47 min down, 1.0 s cycle, 19,271 made, 18,848 good: OEE 74.8 %.
حقائق سريعة
- الفئة: الهندسة والبناء
- يعمل في متصفحك، بلا تسجيل وبلا رفع.
- ما تُدخله يبقى على جهازك.
- متوفر بالإنجليزية.
- آخر مراجعة للمحتوى:
- المصدر الرسمي: Overall equipment effectiveness OEE = availability × performance × quality (Nakajima, Introduction to TPM; ISO 22400-2 KPIs for manufacturing operations management), world-class benchmark 85 %
الأسئلة الشائعة
How is OEE calculated?
Availability × performance × quality.
What is a good OEE?
85 % is world class; 60 % is typical.
Should planned maintenance count as downtime?
It is usually excluded from planned time, but track it separately.
Why is my performance above 100 %?
The ideal cycle time entered is slower than the real best cycle.
What is takt time?
Available time divided by customer demand.
Is my data stored?
No. Nothing is uploaded.