Risk Assessment Matrix Builder (Likelihood × Impact)

List each risk with likelihood and impact from 1 to 5 and an owner, and get scores, bands and a sorted register you can copy.

Funziona nel tuo browser. I tuoi file non lasciano mai il dispositivo. Scopri come verificarlo

…

Come si usa

  1. 1
    List risks

    One per line: risk, likelihood, impact, owner.

  2. 2
    Check scales

    Use 1 to 5 for likelihood and impact.

  3. 3
    Read the register

    See scores, bands and the ranked table.

  4. 4
    Plan treatment

    Assign owners and actions for high and extreme risks.

Informazioni su questo strumento

A risk matrix is the most widely used tool for prioritising risks in projects, events, businesses and public relations. ISO 31000:2018 sets out the risk management process, identify, analyse, evaluate and treat, and IEC 31010:2019 describes the consequence and likelihood matrix as one of the techniques for analysis. Each risk is rated for how likely it is and how severe its impact would be, usually on a scale of 1 to 5, and the two are multiplied into a score from 1 to 25. Scores are grouped into bands that drive action: low risks are accepted and monitored, medium risks get controls, high risks need active management by a named owner, and extreme risks need immediate attention or a change of plan. This builder takes a simple list, one risk per line with likelihood, impact and owner, calculates scores and bands, sorts the register from highest to lowest, and summarises how many risks fall in each band. It works for project risks, event safety, cybersecurity, supplier risk, reputational and PR risks, or cultural and tourism projects, and the table can be copied straight into a report.

Who this is for

Project managers, event organisers, PR and communications teams, compliance and safety officers, and small business owners.

Scales

| Score | Likelihood | Impact | |---|---|---| | 1 | Rare | Insignificant | | 2 | Unlikely | Minor | | 3 | Possible | Moderate | | 4 | Likely | Major | | 5 | Almost certain | Severe |

Define each level in your own terms, for example impact 5 = loss above 10% of profit or serious injury.

Bands

| Score | Band | Action | |---|---|---| | 15–25 | Extreme | Immediate action | | 10–14 | High | Owner and treatment plan | | 5–9 | Medium | Controls and monitoring | | 1–4 | Low | Accept and review |

Treatment options

ISO 31000 lists ways to treat risk: avoid it, reduce likelihood, reduce impact, share it (insurance, contracts) or accept it.

Inherent and residual risk

Score risks before controls (inherent) and after (residual) to show the effect of treatments.

Risk appetite

Before scoring, agree the organisation's risk appetite: how much risk it is willing to accept to achieve its goals. A start-up may accept high market risk but very low legal risk; a hospital very low safety risk. The bands and actions in the matrix should reflect that appetite.

Reporting

Share the top risks, their owners and the status of treatments with management regularly, and record changes in scores over time to show whether controls are working.

Limits of matrices

Matrices simplify. Two risks with the same score can differ greatly; very rare catastrophic risks can be underrated. Use them for prioritising, not precise measurement.

Worked example

Five risks: key supplier failure (3 × 4 = 12, high), data breach (2 × 5 = 10, high), launch delay (4 × 3 = 12, high), staff leaving (9, medium), negative press (4, low). Three high risks need owners and plans.

Limits

A planning aid, not official advice.

Esempio svolto

5 risks: 3 high, 1 medium, 1 low; top: key supplier fails (12).

In breve

Domande frequenti

How is a risk score calculated?

Likelihood times impact, each on a scale of 1 to 5.

What do the bands mean?

They set the level of action: accept, control, manage or act immediately.

Which standard covers risk matrices?

ISO 31000 for risk management and IEC 31010 for assessment techniques.

What is residual risk?

Risk remaining after controls.

How often should I update the register?

Regularly, for example at each project stage or quarterly.

What are the treatment options?

Avoid, reduce, share or accept.

Completamente gratisNessun costo, nessuna registrazione
I file restano privatiTutto funziona nel tuo browser
Facile nella tua linguaDisponibile in molte lingue