Request for Quotation (RFQ) Generator

Enter the buyer, RFQ number and deadline, list the items with specifications and quantities, set terms and evaluation criteria, then record each supplier's prices and print a comparison sheet.

Funziona nel tuo browser. I tuoi file non lasciano mai il dispositivo. Scopri come verificarlo

…

Come si usa

  1. 1
    Enter the buyer

    RFQ number and dates.

  2. 2
    List items

    Spec, quantity, unit.

  3. 3
    Set terms

    Delivery, payment, warranty.

  4. 4
    Add criteria

    With weights.

  5. 5
    Record quotes

    Price and days per line.

  6. 6
    Print comparison

    Lowest complete price.

Informazioni su questo strumento

A request for quotation, or RFQ, asks several suppliers to price the same list of goods or services on the same terms, so the buyer can compare like with like. It is the usual method for purchases that are too large for a single phone call but too small for a full tender, and many organisations require at least three written quotes. A good RFQ numbers each line, gives a clear specification and quantity, says where and when delivery is needed, states payment and warranty terms and explains how quotes will be judged. This generator produces that document and then helps you compare the replies. The first part holds the buyer, contact details, RFQ number, title, issue date, due date and currency. The items table prints each line with a specification, quantity and unit, and leaves blank unit price and total columns for suppliers to fill in. The terms part covers delivery place and terms, the required delivery time, quote validity, payment terms, the warranty you need, evaluation criteria with weights and how to submit. A closing line makes clear that the request is not an order. When quotes arrive, you enter one row per supplier and line with the unit price and delivery days. The comparison sheet multiplies each price by the quantity, totals each supplier, flags lines that were not quoted, shows the longest delivery time and names the lowest complete price.

Who this is for

Procurement officers, office and facilities managers, hospital and school buyers, project engineers and small businesses that buy equipment or services from several suppliers.

Writing specifications

Describe what the item must do, not a brand name, unless compatibility forces it. Include sizes, standards and accessories, and ask suppliers to state any difference from the specification.

Quantities and units

Every line needs a quantity, and the tool warns if one is missing. Use units such as each, set or lot, and treat services such as installation or training as a single lot.

Evaluation criteria

Publishing weights such as price 50%, technical compliance 30%, delivery 10% and warranty 10% tells suppliers what matters and makes your decision easier to defend.

Recording responses

Add one row for each supplier and line number with the unit price and delivery days. A price of 0 means the line was not quoted, so that supplier's total is shown as incomplete.

Reading the comparison

The lowest complete price is only the starting point. A cheaper supplier who left a line out, or who needs much longer to deliver, may cost more once the gap is filled.

Dates and deadlines

The due date should fall after the issue date, and the checks warn if it does not. Allow enough time for suppliers to ask questions and get data sheets.

Limits

A drafting and comparison aid, not an official procurement procedure. Public bodies must follow their own procurement rules and thresholds.

Esempio svolto

RFQ-2026-118 for patient monitors has 4 lines. Medequip Co quotes every line for USD 48,020 (20 x 2,150 + 40 x 48 + 20 x 65 + 1 x 1,800) with 35 days delivery. Vital Systems totals USD 43,400 but leaves the training line unquoted, and CarePoint Supplies totals USD 48,680 with one line missing, so the lowest complete price is Medequip Co at USD 48,020.

In breve

Domande frequenti

What is an RFQ?

A request asking suppliers to price a defined list of items on the same terms.

How is it different from a tender?

An RFQ is simpler and used for smaller purchases; a tender has a formal procedure.

How many quotes should I get?

Many organisations ask for at least three; check your own rules.

What does lowest complete price mean?

The lowest total among suppliers who quoted every line.

Is the RFQ an order?

No. It says clearly that it does not commit the buyer to purchase.

Is my data stored?

Only in your browser.

Completamente gratisNessun costo, nessuna registrazione
I file restano privatiTutto funziona nel tuo browser
Facile nella tua linguaDisponibile in molte lingue