Material Requirements Planning (MRP) Calculator
Set up an item master and bill of materials, enter the master production schedule and open orders, and get the time-phased MRP record for every item with planned orders, lot sizing and expedite messages.
Funziona nel tuo browser. I tuoi file non lasciano mai il dispositivo. Scopri come verificarlo
…
Come si usa
- 1Set the horizon
Choose the number of weeks and the start date of week 1.
- 2Build the item master
Enter each part's lead time, stock, safety stock, scrap and lot rule.
- 3Link the BOM
Add parent and component lines with the quantity per parent.
- 4Enter demand
Type the master schedule for end items and any open orders already due in.
- 5Read the records
Check net requirements, planned releases and any past-due messages for each item.
- 6Act and export
Release the orders, export CSV, view the timeline or print the plan.
Informazioni su questo strumento
Material requirements planning turns a schedule of finished products into a schedule of everything needed to make them. If 60 tables must ship in week 5 and each table needs four legs, then 240 legs must be ready a week earlier, less any legs already in stock, and the order for them must be placed a lead time before that. Doing this by hand for a few items is a classic exercise in operations courses; doing it for a real bill of materials quickly becomes a spreadsheet tangle. This calculator holds the whole plan in one place. The item master stores each part's code, lead time in weeks, stock on hand, allocated stock, safety stock, scrap allowance and lot-sizing rule: lot for lot, a fixed order quantity, or a number of periods of supply, with optional minimum and multiple. The bill of materials links parents to components with a quantity per parent, and the tool works out low-level codes so that each item is planned only once all its parents are known, even when a part is used at several levels. Enter the master production schedule for end items, any independent demand for spare parts, and scheduled receipts for orders already open. The result is the standard MRP record for every item, week by week, with planned order releases, past-due warnings, an indented BOM explosion and a timeline of orders.
The logic of the MRP record
For each week the projected available balance is last week's balance plus scheduled receipts minus gross requirements. When that would fall below safety stock, the shortfall is the net requirement and a planned order receipt is created according to the lot rule; with scrap, the order is grossed up so that the good quantity covers the need. Each planned receipt is offset by the item's lead time to give a planned order release, and those releases, multiplied by the quantity per parent, become the gross requirements of the components. If a release would fall before week 1, the quantity is shown as past due with a message to expedite or replan.
Worked example
The sample plans dining tables over eight weeks from 23 November 2026. Demand is 40, 60, 50 and 30 tables in weeks 3, 5, 7 and 8, and 20 are in stock, so net requirements are 20, 60, 50 and 30 and, with a one-week lead time, assembly orders are released in weeks 2, 4, 6 and 7. Each table needs four legs, giving leg requirements of 80, 240, 200 and 120 in weeks 2, 4, 6 and 7. With 60 legs on hand, a safety stock of 20 and a two-week periods-of-supply rule, the leg orders are 40 due in week 2, 240 in week 4 and 320 in week 6, the last covering weeks 6 and 7 together. Tops are bought in fixed lots of 50: from 30 in stock, receipts of 50 arrive in weeks 4, 6 and 7, released in weeks 2, 4 and 5. Two oak boards per top give board requirements of 100 in weeks 2, 4 and 5; 60 in stock plus an open order of 50 cover week 2, and orders of 90 and 100 are released in weeks 2 and 3. Twelve planned orders result and none is past due.
Limits
This is an infinite-capacity calculation: it does not check whether machines or people can make the planned orders, so pair it with a capacity check before releasing work. It plans in whole weeks and assumes lead times are fixed. It is a planning aid, not an ERP system, and does not post transactions or manage stock.
Esempio svolto
Dining table plan, 8 weeks: assembly orders released in weeks 2, 4, 6 and 7; leg orders of 40, 240 and 320; no past-due orders.
In breve
- Categoria: Aziende e lavoro
- Funziona nel browser, senza registrazione né caricamento.
- Le informazioni che inserisci restano sul tuo dispositivo.
- Disponibile in inglese.
- Contenuto rivisto l'ultima volta il:
- Fonte ufficiale: J. Orlicky, Material Requirements Planning (McGraw-Hill 1975); ASCM Dictionary
Domande frequenti
What is the difference between gross and net requirements?
Gross requirements are the total needed in a week, from the schedule and from parent orders. Net requirements are what is left after stock on hand and scheduled receipts are used, plus whatever is needed to restore safety stock.
What are low-level codes and why do they matter?
A low-level code is the deepest level at which an item appears in any bill of materials. Planning items in that order guarantees that all demand from every parent has been added before a component is planned, so a part used in two products is planned once with both demands.
Which lot-sizing rule should I choose?
Lot for lot orders exactly the net requirement and keeps stock lowest. Fixed order quantity suits pack sizes or supplier minimums. Periods of supply combines several weeks of need into one order to save set-up or delivery costs. Minimum and multiple apply on top of any rule.
What does a past-due order mean?
The order would have had to be released before week 1 to arrive in time. The tool shows the quantity and adds it to the components in week 1, but in practice you must expedite it, shorten the lead time or move the demand.
How is scrap handled?
Enter the expected scrap percentage for an item. Each planned order is increased so that the good quantity after scrap still covers the requirement, and only the good quantity is added to projected available stock.
Can I take the plan into a spreadsheet?
Yes. Export the full MRP records or just the list of planned orders as CSV, print the records, or save the whole plan as a file to reopen later or share with a colleague.