Interim Valuation and Application for Payment Builder (JCT)
Value the work to date line by line, add variations and materials, take off retention and previous certificates, apply VAT and CIS and print the application.
Funziona nel tuo browser. I tuoi file non lasciano mai il dispositivo. Scopri come verificarlo
…
Come si usa
- 1Set up the project
Add the project, employer, contractor, contract form and the QS or contract administrator.
- 2Enter the contract lines
Type or import each contract line with its value and set the percentage complete.
- 3Add variations and materials
List each instruction with status and value, and the materials on site or listed off site.
- 4Set retention and VAT
Choose the retention percentage, the stage, the VAT treatment and any CIS rate.
- 5Check the summary
Read the gross valuation, retention, previous certificates and net due, and any warnings.
- 6Print the application
Print or download the application, then use next application to roll forward next month.
Informazioni su questo strumento
Every month on a building contract the contractor sets out what it thinks it has earned, and the quantity surveyor or contract administrator values it. The sums are simple in principle but easy to get wrong in a spreadsheet: work done as a percentage of each contract line, variations that are agreed or still being argued about, materials delivered to site and listed items held elsewhere, loss and expense and fluctuations that are paid without retention, a retention percentage that halves at practical completion, and the running total of what has already been certified. Then VAT has to be added, or left to the customer under the construction reverse charge, and a subcontractor may have CIS deducted from the labour element. This builder keeps each project's contract breakdown and builds the application from it. Every line shows the value earned, the summary shows gross valuation, retention, previous certificates and the net sum due, and warnings point out unlisted off-site materials and unagreed variations. When the month is done, the next application button carries this certificate into the previous ones and clears the materials list ready for next month.
What goes into the gross valuation
The gross valuation is the total value of work properly done to date, not just this month. Measured work is each contract line's value times the percentage complete. Variations are valued the same way, with a status so the employer's surveyor can see which are agreed. Materials delivered to site and adequately protected are included; materials stored off site are only included if they are listed items with proof of ownership and insurance, as the contract requires. Loss and expense and fluctuations are added, but outside the retention.
Retention, VAT and CIS
Retention is a percentage held back from the value subject to retention, 3% by default in JCT contracts. Half is released at practical completion and the rest when the certificate of making good is issued, so choose the stage. Previous certificates are deducted to give the net amount due. Standard-rated work then carries 20% VAT; if the customer is a VAT-registered contractor who is not an end user, the domestic reverse charge applies and no VAT is added. A subcontractor paid under CIS may have 20% or 30% deducted from the labour part of the payment.
Worked example
The sample extension has a contract sum of £600,000. Measured work comes to £264,350, 44.06% of the contract, from preliminaries at 45%, substructure complete, the frame at 80% and so on. Variations add £9,550: an agreed steel beam of £6,400 and a submitted drainage run of £3,150, while the triple glazing instruction is not yet started. Roof trusses on site and listed windows at the supplier add £22,700, but £3,600 of bricks at the merchant is left out because they are not listed. With £2,500 of loss and expense the gross valuation is £299,100. Retention at 3% on £296,600 is £8,898, previous certificates total £199,270, and the net due is £90,932. VAT at 20% is £18,186.40, so £109,118.40 is payable. At practical completion the retention would halve to £4,449.
Limits
This is a valuation aid, not a payment certificate and not legal or tax advice. The contract administrator or quantity surveyor values the work under your contract, whose clause numbers and rules may differ. It does not check that percentages are fair, value variations for you or replace the payment and pay less notices the Construction Act requires.
Esempio svolto
Gross £299,100 less 3% retention £8,898 less previous certificates £199,270 = £90,932 net; plus VAT £18,186.40 = £109,118.40 payable.
In breve
- Categoria: Aziende e lavoro
- Funziona nel browser, senza registrazione né caricamento.
- Le informazioni che inserisci restano sul tuo dispositivo.
- Disponibile in inglese.
- Contenuto rivisto l'ultima volta il:
- Fonte ufficiale: JCT 2024 Standard Building, Intermediate and Design and Build contracts; HMRC VAT domestic reverse charge guidance
Domande frequenti
Is retention taken from loss and expense?
Not in JCT contracts: loss and expense and fluctuations are normally paid without retention. The builder keeps them in a separate line that is added after retention is worked out.
When is retention released?
Half at practical completion and the rest when the certificate of making good defects is issued after the rectification period. Choose the stage and the retention figure changes.
Can off-site materials be included?
Only listed items that meet the contract's conditions, usually proof of ownership, separate storage, insurance and sometimes a bond. Untick the listed box and the builder leaves them out with a warning.
When does the reverse charge apply?
When a VAT-registered contractor supplies standard or reduced rated construction services to another VAT-registered business that reports under CIS and is not an end user. The customer then accounts for the VAT.
Can I import my contract breakdown?
Yes. Import a CSV with type, ref, description, value, percentage and status columns, or export the current lines, edit them in a spreadsheet and import them back.
What does next application do?
It increases the application number, adds this application's net figure to previous certificates with today's valuation date and clears the materials list, so you only update the percentages.