Garment SMV and Line Efficiency Calculator

Paste the operation breakdown of a style, add operators, minutes and today's output, and see efficiency, targets, the bottleneck and how to rebalance the sewing line.

Funziona nel tuo browser. I tuoi file non lasciano mai il dispositivo. Scopri come verificarlo

…

Come si usa

  1. 1
    Enter the style

    Name, working minutes and any overtime.

  2. 2
    Paste the bulletin

    Each operation with machine, SMV and operators.

  3. 3
    Set the plan

    Planned efficiency and the day's actual output.

  4. 4
    Read the results

    Efficiency, targets, takt time and the bottleneck.

  5. 5
    Rebalance

    Compare current operators with the suggested split.

  6. 6
    Export

    Download the operation bulletin as CSV.

Informazioni su questo strumento

In apparel factories every style comes with an operation bulletin: the list of sewing, finishing and helper operations with a standard minute value, or SMV, for each. SMV is the time a trained operator needs for one operation at a normal pace with allowances, measured by time study or from a predetermined system such as GSD. Add the SMVs and you have the style's work content. From that, a line chief or industrial engineer works out the targets everyone talks about on the floor: how many pieces the line should make in an hour, how efficient it was yesterday and which operation is holding it back. This calculator does those sums. Enter each operation with its machine type, SMV and the operators assigned, then the working minutes, overtime, planned efficiency and the day's actual output. It returns total SMV and manpower, the day's target at 100% and the hourly target at your planned efficiency, takt time, the actual line efficiency, and each operation's capacity an hour. The slowest operation is named as the bottleneck, and a suggested operator split, built by giving each extra operator to whichever operation is slowest, shows the best output that the same headcount could reach.

The formulas

Line efficiency is output × SMV ÷ (manpower × working minutes): earned minutes divided by available minutes. The target a day at 100% is available minutes ÷ SMV, and the hourly target is manpower × 60 ÷ SMV × planned efficiency. Takt time is the seconds available for each piece at that target. An operation's capacity an hour is operators × 60 ÷ its SMV; the lowest capacity is the most the whole line can produce, however hard the other operators work.

Balancing the line

The balancing table shows, for every operation, the operators now, the capacity at 100% and at your planned efficiency, the theoretical operators needed for the target and a suggested whole number. Balancing efficiency compares total SMV with manpower times the longest cycle time per operator; 85% and above is a well-balanced line. The machine summary counts overlock, flatlock, single-needle and other machines needed for the current and the suggested plan, which helps when booking machines for the next style.

Scenarios

Compare the current line against a rebalanced one, two hours of overtime, or efficiency targets of 55%, 65% and 75%. A polo shirt preset shows a heavier style. The labour cost per piece uses the average daily cost of a worker and the day's output, a quick check on the CM price.

Worked example

The default basic T-shirt has 11 operations with a total SMV of 4.85 minutes and 15 operators working 480 minutes. Yesterday the line made 780 pieces, so efficiency is 780 × 4.85 ÷ (15 × 480) = 52.5%. At a planned 65% the hourly target is 15 × 60 ÷ 4.85 × 65% = about 121 pieces. Thread trimming, with one helper on a 0.60 minute job, caps the line at 100 pieces an hour; the suggested split moves an operator from care labels to trimming and lifts the limit to 133 an hour.

Limits

The suggested split is arithmetic, not a replacement for an industrial engineer: it does not know operator skills, machine availability, learning curves or quality problems. SMVs must come from proper time study or a predetermined system for the results to mean anything. Efficiency definitions also vary between factories, so state the formula when you report.

Esempio svolto

780 pieces × 4.85 SMV ÷ (15 × 480 minutes) = 52.5% line efficiency; the target at 65% is about 121 an hour.

In breve

Domande frequenti

What is SMV?

Standard minute value: the minutes a trained operator needs for one operation at normal pace, including allowances. The style's SMV is the sum of all operations.

How is line efficiency calculated?

Output × SMV ÷ (operators × working minutes) × 100. It compares the minutes the output is worth with the minutes the line was paid for.

What is the bottleneck?

The operation with the lowest capacity an hour, operators × 60 ÷ SMV. The line cannot produce more than it, so balancing starts there.

Should helpers count in manpower?

Count everyone on the line whose time is paid for the style, including helpers and ironers, if you want a true labour efficiency. State your choice when comparing lines.

What efficiency should I plan for?

A new style often starts at 35–45% and climbs over the first days; mature knit lines commonly run at 55–70%.

Is my operation bulletin uploaded?

No. All calculations happen in this browser.

Completamente gratisNessun costo, nessuna registrazione
I file restano privatiTutto funziona nel tuo browser
Facile nella tua linguaDisponibile in molte lingue