CDM 2015 Construction Phase Plan Builder
Fill in the project, duty holders, site rules, risks and controls, welfare and emergency details; the builder checks the F10 thresholds and prints the plan.
Funziona nel tuo browser. I tuoi file non lasciano mai il dispositivo. Scopri come verificarlo
…
Come si usa
- 1Choose a preset
Start from the domestic extension, commercial fit-out or small job preset closest to your project.
- 2Describe the project
Enter the site, the work, the start date, duration, working days, peak workforce and person-days.
- 3Name the duty holders
Add the client, principal designer, principal contractor and the other contractors and designers.
- 4Set rules and risks
Edit the site rules, management arrangements and the table of significant risks and controls.
- 5Add welfare and emergencies
Describe the welfare facilities, first aid, nearest A&E, assembly point and fire procedure.
- 6Check and print
Read the checks, record the F10 if notifiable, and print the plan, F10 checklist and induction register.
Informazioni su questo strumento
Every construction project in Great Britain, from a kitchen extension to an office fit-out, needs a construction phase plan before work starts on site. The Construction (Design and Management) Regulations 2015 make the principal contractor, or the only contractor on a small job, responsible for drawing it up. The plan does not need to be long, but it must be specific: who the client, principal designer and principal contractor are, the site rules, the significant risks of this job and how they will be controlled, the welfare facilities, and what happens in an emergency. Larger projects must also be notified to the Health and Safety Executive on form F10 before the construction phase begins. This builder walks through each section with editable sample text for a typical domestic extension, a notifiable commercial fit-out and a small single-contractor job. The F10 test is worked out from the working days, the peak number of workers and the person-days you enter. The risk table has a column for the Schedule 3 categories of work with particular risks, and the checks look for missing appointments, missing controls, welfare gaps, asbestos and an F10 sent too late.
When a project must be notified
Regulation 6 says a project is notifiable if the construction work is scheduled to last longer than 30 working days and have more than 20 workers working simultaneously at any point, or to exceed 500 person-days. Either test is enough. The client, or for a domestic client the contractor who takes on the client duties, sends the F10 to HSE as soon as practicable before the construction phase begins and keeps a copy displayed on site. Notification does not change the duties; even a three-day job needs a plan.
What the plan should contain
HSE's guidance asks for a description of the project and the key dates, the management arrangements including communication and site rules, the arrangements for controlling significant risks, and welfare. Schedule 3 lists work that carries particular risks, including excavations where there is a risk of burial, work near high voltage lines, work with explosives and the assembly or dismantling of heavy prefabricated components; if any apply, the plan must say how they are managed. Schedule 2 sets the minimum welfare: toilets, washing facilities, drinking water, changing and rest areas.
Worked example
The sample domestic extension in Sheffield has a 16-week programme with 80 working days, at most 8 workers on site at once and an estimated 420 person-days. It is long enough for the first test's 30 days but has nowhere near 20 people at once, and 420 person-days is under 500, so the plan states that it is not notifiable. The commercial fit-out preset has 70 working days, a peak of 28 workers and 1,450 person-days, so it is notifiable under both tests and the F10 date and reference are recorded. A job of 31 working days with 21 people at the peak is notifiable; one of 30 days with 25 people is not. All three presets pass the checks.
Limits
This builder helps you write and check the plan; it does not make the work safe, and it is not legal advice. The duty holder remains responsible for a plan that fits the real site, and for risk assessments, method statements, temporary works designs and asbestos surveys. Follow HSE guidance L153 and the industry guidance for your trade, and submit the F10 on the HSE website.
Esempio svolto
Domestic extension: 80 days, peak 8, 420 person-days: not notifiable. Fit-out: 70 days, peak 28, 1,450 person-days: notifiable on both tests.
In breve
- Categoria: Aziende e lavoro
- Funziona nel browser, senza registrazione né caricamento.
- Le informazioni che inserisci restano sul tuo dispositivo.
- Disponibile in inglese.
- Contenuto rivisto l'ultima volta il:
- Fonte ufficiale: Construction (Design and Management) Regulations 2015 (SI 2015/51); HSE guidance L153
Domande frequenti
Who writes the construction phase plan?
The principal contractor, or the contractor if there is only one. The principal designer helps by passing on pre-construction information. For a domestic client the client duties pass to the contractor or principal contractor.
Does a small job need a plan?
Yes. Every project needs a construction phase plan, but it should be proportionate: a short plan for a simple job is fine as long as it covers the real risks, welfare and emergency arrangements.
When must an F10 be sent?
As soon as practicable before the construction phase begins, if the project will last more than 30 working days with more than 20 workers at the same time, or will exceed 500 person-days.
What are Schedule 3 risks?
Work with particular risks listed in Schedule 3 of CDM 2015, such as the risk of burial or falling from height, chemical or biological exposure, radiation, high voltage lines, drowning, tunnels, diving, compressed air, explosives and heavy prefabricated components.
When are a principal designer and principal contractor needed?
Whenever more than one contractor will work on the project. The client must appoint them in writing; if it does not, the client takes on their duties.
What welfare must be provided?
Schedule 2 requires toilets, washing facilities with hot and cold water, drinking water, somewhere to change and store clothing, and a rest area. They must be available from the start of work.