Calculadora de precios de margen y variación del constructor

Enumere cada variación con su costo y estado de aprobación, establezca su margen y vea los precios de la variación, el GST y el total del nuevo contrato.

Se ejecuta en tu navegador. Tus archivos nunca salen de tu dispositivo. Cómo comprobarlo

…

Cómo hacerlo

  1. 1
    Entra en el contrato

    Escriba el importe original del contrato.

  2. 2
    Establezca el margen

    Escriba el margen para las variaciones.

  3. 3
    Variaciones de la lista

    Escriba cada uno como número, descripción, costo y aprobado sí o no.

  4. 4
    Leer el registro

    Ver precios, GST, estado y el nuevo importe del contrato.

  5. 5
    Obtener la firma de fuera

    Enviar las variaciones pendientes al propietario para su aprobación por escrito.

Sobre esta herramienta

Variations are changes to the work in a building contract: an upgraded benchtop, extra power points, rock found during excavation, or an item the owner deletes. They are one of the main causes of disputes between builders and owners. Home building laws in every state require variations to be in writing, with a description and price, and agreed by the owner before the work is done, with limited exceptions. Builders usually add a margin to the cost of a variation to cover overheads and profit, often 15 to 25%, and then GST at 10%. This calculator prices each variation with your margin and GST, keeps a register showing which are approved and which are still pending, works out the adjusted contract sum, and shows how much the variations have changed the original price.

Who this is for

Builders, renovators and trade contractors who price variations, and home owners who want to check variation claims.

How a variation is priced

Variation price = cost of labour and materials × (1 + margin) + GST at 10%. For a credit, such as a deleted item, the cost is entered as a negative number and no margin is added, though contracts can say otherwise. Your contract may set the margin for variations; use that figure.

Entering variations

Write one variation per line: number, description, cost excluding GST and margin, and whether the owner has approved it (yes or no). For example, `V1, Upgrade benchtop to stone, 4200, yes`.

The register

The table shows each variation's cost, the price after margin, the GST and the total, with its status. The summary gives: - the original contract sum including GST, - approved variations, - the new contract sum, - pending variations still to be agreed, - the percentage change from the original price, - the margin earned on approved variations.

Getting variations right

- Put every variation in writing before the work, with a description, price and any change to the completion date. - Get the owner's signature or written approval. - Number variations and keep a running register. - Include variations in progress claims only once approved. Some states set rules for variations required by an authority or emergency, and some limit when a builder can claim for work done without a signed variation.

For owners

Ask for the cost breakdown and the margin used. Compare the price with what you would pay for the item separately. Check whether a variation also extends the completion date.

Worked example

On a A$385,000 contract including GST, with a 20% margin: an upgraded stone benchtop at A$4,200 cost, six extra power points at A$780 and a garden shed deleted for a A$2,400 credit add A$3,934 to the contract, a 1.0% increase. Rock excavation at A$6,500 cost (A$8,580 with margin and GST) is pending.

Limits

An estimate, not legal advice. Your contract terms and your state's home building laws decide how variations must be made and paid.

Ejemplo práctico

Tres variaciones aprobadas añaden A$3,934 a un contrato de A$385,000; uno por valor de A$8,580 está pendiente.

Datos rápidos

Preguntas frecuentes

¿Cómo hacen los constructores las variaciones de precios?

El costo más un margen, a menudo del 15 al 25%, más el GST.

¿Tiene que haber variaciones por escrito?

Sí, las leyes de construcción en cada estado requieren variaciones escritas en la mayoría de los casos.

¿Se añade el GST a las variaciones?

Sí, al 10% para un constructor registrado.

¿Cómo se manejan los elementos eliminados?

Como crédito, introduzca un coste negativo.

¿Puede un constructor cobrar por variaciones no firmadas?

A menudo no, o sólo en casos limitados; compruebe la ley de su estado.