Late Payment Interest and Liquidated Damages Calculator

Choose UK, EU or contract rules, enter the debt, due and paid dates and the reference rate, then contract value, daily rate, cap and delay for damages.

S'executa al teu navegador. Els fitxers mai no surten del dispositiu. Mira com comprovar-ho

…

Com es fa

  1. 1
    Choose the rules

    Pick UK statute, EU directive or contract rate.

  2. 2
    Enter the debt

    Type the amount, due date and payment date.

  3. 3
    Enter the rate

    Type the reference rate or contract rate.

  4. 4
    Add delay damages

    Enter contract value, daily rate, cap and delay days.

  5. 5
    Read the claim

    See interest, fixed sum and damages.

Sobre aquesta eina

Businesses that pay late are using their suppliers as a free bank. Many countries give creditors a statutory right to interest and compensation in business-to-business deals. In the United Kingdom, the Late Payment of Commercial Debts (Interest) Act 1998 lets a supplier claim simple interest at 8% above the Bank of England's reference rate (the base rate in force on 30 June or 31 December before the debt became overdue), plus a fixed sum for recovery costs: £40 for debts under £1,000, £70 for debts of £1,000 to £9,999.99 and £100 for debts of £10,000 or more. Across the European Union, Directive 2011/7/EU requires a statutory rate of at least the European Central Bank's main refinancing rate plus 8 percentage points and a minimum fixed compensation of €40. This calculator counts the days between the due date and payment, applies the statutory or contractual rate on a 365-day or 360-day basis, adds the fixed sum and shows the total claim. A second section calculates liquidated damages for delay, common in construction and supply contracts: contract value times a daily percentage times days of delay, limited by the contractual cap. Courts enforce such clauses when they protect a legitimate interest and are not out of all proportion, the test set by the UK Supreme Court in Cavendish v Makdessi (2015).

Who this is for

Freelancers and small suppliers chasing overdue invoices, credit controllers, contract managers and construction professionals.

Statutory interest

| Regime | Rate | Fixed compensation | |---|---|---| | UK Late Payment Act | Reference rate + 8% | £40, £70 or £100 by debt size | | EU Directive 2011/7/EU | ECB rate + 8 points (minimum) | At least €40 | | Contract | Agreed rate | As agreed |

Enter the reference rate in force for your period: the Bank of England base rate (UK) or the ECB main refinancing rate (EU). The default is only an example.

Day count

Interest is simple, not compound: debt × rate × days ÷ 365. Some contracts use 360 days.

When interest starts

In the UK, from the agreed due date or, if none, 30 days after delivery or the invoice. Contracts can set their own substantial remedy instead of the statutory one.

Liquidated damages

Daily rate × contract value × days of delay, limited by any cap (often 5% to 15% of the contract value). They replace the need to prove actual loss for delay.

Worked example

A £12,000 invoice due on 31 March 2026 and paid on 29 July 2026 is 120 days late. At 4% + 8% = 12%, interest is £473.42, about £3.95 a day, plus a fixed sum of £100: £573.42. For a 250,000 contract with damages of 0.1% a day capped at 10%, 45 days of delay gives 11,250, below the 25,000 cap.

Limits

A calculation aid, not legal advice. Check the contract and current rates.

Exemple resolt

£12,000, 120 days late at 12%: £473.42 interest + £100 = £573.42.

En resum

Preguntes freqüents

What interest can I charge on a late invoice in the UK?

8% above the Bank of England reference rate, plus a fixed sum, for business-to-business debts.

What are the UK fixed sums?

£40 under £1,000, £70 from £1,000 to £9,999.99 and £100 from £10,000.

What is the EU rule?

At least the ECB rate plus 8 points and a minimum of €40 compensation.

Is late payment interest compound?

No, statutory interest is simple.

Are liquidated damages enforceable?

Generally yes, unless they are out of all proportion to the legitimate interest protected.

Does it apply to consumers?

No, these statutory rights apply between businesses and public authorities.